Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package II- Design , construction of 32 Laks ltr, 7 Lakhs Ltr, OHSRs and 12 Lakhs Ltr capacity GLSR , Supplying and laying of Raw water Pumping main , Clear water Gravity main, Raw water , clear water pumpsets, supply and erection of Transformers. Panchayath in Malappuram District

Project Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package II- Design , construction of 32 Laks ltr, 7 Lakhs Ltr, OHSRs and 12 Lakhs Ltr capacity GLSR , Supplying and laying of Raw water Pumping main , Clear water Gravity main, Raw water , clear water pumpsets, supply and erection of Transformers. Panchayath in Malappuram District
Project Code MLPJJM092110135P2
Type Package
Main Project Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba Panchayath in Malappuram District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Package II- Design , construction of 32 Laks ltr, 7 Lakhs Ltr, OHSRs and 12 Lakhs Ltr capacity GLSR , Supplying and laying of Raw water Pumping main , Clear water Gravity main, Raw water , clear water pumpsets, supply and erection of Transformers.
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 24370
TS Number 15777/21-22
Technical specification Construction of Service reservoirs, pumping &Transmission main, supply pumpsets and transformers , erection

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/05/2022
Scheduled date of Completion as per agreement 25 Mar 2023
Expected date of Completion 31/03/2023

Processing Dates

TS Date 21 Dec 2021
Estimate Approval 21 Dec 2021
NIT Approval 19 Jan 2022
Tender Closing 25 Jan 2022
Technichal Pre-Qualification 19 Feb 2022
Price bid opening 04 Mar 2022

Approval Dates

Workorder Date 26 Mar 2022
NA 18 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn EE
Date: 27/06/2025

Work in progress | 90% Completed

7LL OHSR @ Bidavumala Plastering compleated, 32 LL OHSR @ Kainassarykotta plastering completed,12 LL Vellappara GLSR Completed , pipe supplied. Clear water Pumping main 500 mm DI pipe laying in progress-3222 m completed,300 mm gravity main -150 m completed,200 mm CWPM-1025 m Completed, Transformer and VT pump set supplied.

Malappuram Project Dn
Date: 13/06/2025

Work in progress | 90% Completed

7LL OHSR @ Bidavumala Plastering compleated, 32 LL OHSR @ Kainassarykotta plastering completed,12 LL Vellappara GLSR Completed , pipe supplied. Clear water Pumping main 500 mm DI pipe laying in progress-3222 m completed,300 mm gravity main -150 m completed,200 mm CWPM-1025 m Completed, Transformer and VT pump set supplied.