- Home
- Jal Jeevan Mission- 21-22- CWSS to Thazh...
Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package II- Design , construction of 32 Laks ltr, 7 Lakhs Ltr, OHSRs and 12 Lakhs Ltr capacity GLSR , Supplying and laying of Raw water Pumping main , Clear water Gravity main, Raw water , clear water pumpsets, supply and erection of Transformers. Panchayath in Malappuram District
Project |
Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba - Package II- Design , construction of 32 Laks ltr, 7 Lakhs Ltr, OHSRs and 12 Lakhs Ltr capacity GLSR , Supplying and laying of Raw water Pumping main , Clear water Gravity main, Raw water , clear water pumpsets, supply and erection of Transformers. Panchayath in Malappuram District |
Project Code |
MLPJJM092110135P2 |
Type |
Package |
Main Project |
Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba Panchayath in Malappuram District
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Package II- Design , construction of 32 Laks ltr, 7 Lakhs Ltr, OHSRs and 12 Lakhs Ltr capacity GLSR , Supplying and laying of Raw water Pumping main , Clear water Gravity main, Raw water , clear water pumpsets, supply and erection of Transformers. |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
24370 |
TS Number |
15777/21-22 |
Technical specification |
Construction of Service reservoirs, pumping &Transmission main,
supply pumpsets and transformers , erection |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
20/05/2022 |
Scheduled date of Completion as per agreement |
25 Mar 2023 |
Expected date of Completion |
31/03/2023 |
Processing Dates
TS Date |
21 Dec 2021 |
Estimate Approval |
21 Dec 2021 |
NIT Approval |
19 Jan 2022 |
Tender Closing |
25 Jan 2022 |
Technichal Pre-Qualification |
19 Feb 2022 |
Price bid opening |
04 Mar 2022 |
Approval Dates
Workorder Date |
26 Mar 2022 |
NA |
18 Apr 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Project Dn EE |
Date: 27/06/2025 |
Work in progress | 90% Completed
7LL OHSR @ Bidavumala Plastering compleated, 32 LL OHSR @ Kainassarykotta plastering completed,12 LL Vellappara GLSR Completed , pipe supplied. Clear water Pumping main 500 mm DI pipe laying in progress-3222 m completed,300 mm gravity main -150 m completed,200 mm CWPM-1025 m Completed, Transformer and VT pump set supplied.
Malappuram Project Dn |
Date: 13/06/2025 |
Work in progress | 90% Completed
7LL OHSR @ Bidavumala Plastering compleated, 32 LL OHSR @ Kainassarykotta plastering completed,12 LL Vellappara GLSR Completed , pipe supplied. Clear water Pumping main 500 mm DI pipe laying in progress-3222 m completed,300 mm gravity main -150 m completed,200 mm CWPM-1025 m Completed, Transformer and VT pump set supplied.