Jaljeevan Mis sion 2020-21-Laying distribution system and providing FHTC's inVallappuzha Panchayath

Project Jaljeevan Mis sion 2020-21-Laying distribution system and providing FHTC's inVallappuzha Panchayath
Project Code PKDJJM09198047
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jaljeevan Mission 2020-21-Laying distribution system and providing FHTC's inVallappuzha Panchayath
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 277500000
AS Number Go (Rt)No.777/2020/WRD
TS Amount (Rs) 262100000
TS Number 13126/2020-2021
Total Bill Submitted (Rs) 202799398
Total Bill Paid (Rs) 202799398
Population Benefitted 25000
Capacity in MLD 5.00
Actual Project Completion Date 31 May 2023
Coverage Vallappuzha G P
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jaljeevan Mis sion 2020-21-Laying distribution system and providing FHTC's inVallappuzha Panchayath Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 May 2024 104.007/120 km completed. Remaining DI & PVC pipe laying in progress. HTC 3131 /5746 progressing. Palakkad Proj AE 3
17 May 2024 104.007/120 km completed. Remaining DI & PVC pipe laying work going, PWD road (Vaniyamkulam Vallappuzha road stretch-3 work started,140mm 10kg pvc pipe work, vallappuzha - vaniyamkulam pwd road, kuruvattur. HTC 3131 /5746 progressing. Palakkad Project Dn AEE3
15 May 2024 103.904/120 km completed. Remaining DI & PVC pipe laying work going, PWD road (Vaniyamkulam Vallappuzha road stretch-3 work started,140mm 10kg pvc pipe work, vallappuzha - vaniyamkulam pwd road, kuruvattur. HTC 3131 /5746 progressing. Palakkad Project Dn AEE3
13 May 2024 103.8265/120 km completed. Remaining DI & PVC pipe laying work going, PWD road (Vaniyamkulam Vallappuzha road stretch-3 work started,140mm 10kg pvc pipe work, vallappuzha - vaniyamkulam pwd road, kuruvattur. HTC 3131 /5746 progressing. Palakkad Project Dn AEE3
10 May 2024 103.6345/120 km completed. Remaining DI & PVC pipe laying work going, PWD road (Vaniyamkulam Vallappuzha road stretch-3 work started,140mm 10kg pvc pipe work, vallappuzha - vaniyamkulam pwd road, kuruvattur. HTC 3131 /5746 progressing. Palakkad Project Dn AEE3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/04/2021
Scheduled date of Completion of the Project 26 Oct 2021
Expected date of Completion 31/05/2024

Processing Dates

AS Date 24 Dec 2020
TS Date 29 Dec 2020

Other details

Project Officers View