| Project | RKI-Supply and fixing of Surveillance mechanism for automated pumping stations at RWSS to Kottayam mouveri |
|---|---|
| Project Code | KNRRKI042213865P1 |
| Type | Package |
| Main Project | REBUILD-Installation of Surveillance mechanism and Reserve Module-Supply and fixing of Surveillance mechanism for automated pumping stations at RWSS to Kottayam mouveri-General Civil Work |
| Funding Agency | RKI |
| Category | RKI |
| Type of scheme | Others |
| Scheme | 5475-00-115-94-05 |
| Description | Supply and fixing of Surveillance mechanism for automated pumping stations at RWSS to Kottayam mouveri |
| Status | On-going |
| District | Kannur |
| Executing Office | Koothuparambu PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 20000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/5871/2022_6_4_3 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 24/03/2023 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 30/04/2023 |
| TS Date | 24 Mar 2023 |
|---|
| Koothuparambu PH Sn AE |
| Date: 12/05/2023 |
Work has been completed | 100% Completed
Work completed,bill under preperation .
| Koothuparambu PH Sn AE |
| Date: 04/05/2023 |
Work in progress | 70% Completed
Work in progress.