- JJM - CIVIL WORK and RENOVATION OF QUALI...
JJM - CIVIL WORK and RENOVATION OF QUALITY CONTROL DISTRICT LAB AT KOTTAYAM
Project |
JJM - CIVIL WORK and RENOVATION OF QUALITY CONTROL DISTRICT LAB AT KOTTAYAM |
Project Code |
KTMJJM08204719 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM - CIVIL WORK and RENOVATION OF QUALITY CONTROL DISTRICT LAB AT KOTTAYAM |
Status |
Completed |
District |
Kottayam |
Executing Office |
Kottayam QC Sn |
AS Amount (Rs) |
2463000
|
AS Number |
G.O.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
500000 |
TS Number |
TS/2020-2021/2020/21179 |
Total Bill Submitted (Rs) |
295749 |
Total Bill Paid (Rs) |
320321 |
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - CIVIL WORK and RENOVATION OF QUALITY CONTROL DISTRICT LAB AT KOTTAYAM |
Kottayam QC Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Mar 2022 |
work completed in march 2021 |
Thiruvalla Quality AEE |
|
29 Mar 2022 |
work completed |
Thiruvalla Quality AEE |
|
19 Mar 2021 |
60% completed. |
Thiruvananthapuram QC Dn - EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/01/2021 |
Scheduled date of Completion of the Project |
28 Mar 2021 |
Expected date of Completion |
28/03/2021 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
06 Oct 2020 |