Project | Deposit K S H B - Providing water connection to quarters for Gov. servants |
---|---|
Project Code | WYDDEPO022415748 |
Type | Main project |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit K S H B - Providing water connection to quarters for Gov. servants |
Status | On-going |
District | Wayanad |
Executing Office | Mananthavady PH Sn |
AS Amount (Rs) | 880000 |
AS Number | D1/RHS/MNDYHS/2023 Vol 1 |
TS Amount (Rs) | 880000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/17009/2023_26_2_1 |
Total Bill Submitted (Rs) | 1 |
Total Bill Paid (Rs) | |
Population Benefitted | 500 |
Capacity in MLD | 1.00 |
Actual Project Completion Date | Date is not specified |
Coverage | Providing water connection to quarters for Gov. servants |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 May 2024 | Awaiting for pwd permission | Mananthavady PH Sn - AE | |
04 May 2024 | Awaiting for pwd permission | Mananthavady PH Sn - AE | |
04 May 2024 | Demand note issued from PWD | Mananthavady PH Sn - AE | |
30 Apr 2024 | Awaiting for pwd permission | Mananthavady PH Sn - AE | |
22 Apr 2024 | Awaiting for pwd permission | Mananthavady PH Sn - AE |
Date of start of Project | 14/03/2024 |
---|---|
Scheduled date of Completion of the Project | 13 Jun 2024 |
Expected date of Completion | 13/06/2024 |
AS Date | 05 Feb 2024 |
---|---|
TS Date | 15 Feb 2024 |
Project Officers | View |
---|