State Plan 2021-22 - Providing sewage facility / rehabilitation of damaged line in 6-branch lanes at Athani, Vanchiyoor

Project State Plan 2021-22 - Providing sewage facility / rehabilitation of damaged line in 6-branch lanes at Athani, Vanchiyoor
Project Code TVMGOK10218311
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2021-22 - Providing sewage facility / rehabilitation of damaged line in 6-branch lanes at Athani, Vanchiyoor
Status Completed
District Thiruvananthapuram
Executing Office Kuriathy Sewerage Sn 1
AS Amount (Rs) 2750000
AS Number KWA/JB/PIU1/AE1/12/2021
TS Amount (Rs) 2680000
TS Number 12733/2021-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 500
Capacity in MLD 0.10
Actual Project Completion Date 19 Apr 2022
Coverage Athani lane in vanchiyoor ward
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2021-22 - Providing sewage facility / rehabilitation of damaged line in 6-branch lanes at Athani, Vanchiyoor Kuriathy Sewerage Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Apr 2022 Work Completed. Kuriathy Sewerage Sn1 AE
16 Apr 2022 98%: All work in 5 branches out of 6 completed. Work of extension line in the 5th branch instead of 6th branch in progress. Connection to main MH in KRFB road done, restoration concrete and one MH work pending. (Total - 335/340.5 M pipe laying and 21/24 MH completed). Kuriathy Sewerage Sn1 AE
11 Apr 2022 95%: All work in 5 branches out of 6 completed. Work of extension line in the 5th branch instead of 6th branch in progress. Restoration concrete work in progress for 5th branch line. (Total - 335/340.5 M pipe laying and 20/24 MH completed). Kuriathy Sewerage Sn1 AE
07 Apr 2022 90%: All work in 4 branches out of 6 completed. Pipe laying completed and MH construction in progress at 5th branch near Vanchiyoor junction. 80/80M pipe laying and 5/5 MH construction completed, extra 20m extension work with extra 2 MHs as per councilors request in progress, restoration concrete pending. (Total - 330/340.5 M pipe laying and 18/24 MH completed). Kuriathy Sewerage Sn1 AE
04 Apr 2022 86%: All work in 4 branches out of 6 completed. Pipe laying completed and MH construction in progress at 5th branch near Vanchiyoor junction. 80/80M pipe laying and 5/5 MH construction completed, extra 20m extension work as per councilors request in progress, restoration concrete pending. (Total - 315/340.5 M pipe laying and 17/24 MH completed). Kuriathy Sewerage Sn1 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/12/2021
Scheduled date of Completion of the Project 01 Jun 2022
Expected date of Completion 20/05/2022

Processing Dates

AS Date 25 Oct 2021
TS Date 09 Nov 2021

Other details