Deposit work - Smart city Thiruvananthapuram Ltd - Reconstruction / maintenance of sewerage system from Music college to MN Smarakam road (Model school junction to Mettukada Road ID -PWD -PH-4B - 142c) due to work carried out by smart city
Project |
Deposit work - Smart city Thiruvananthapuram Ltd - Reconstruction / maintenance of sewerage system from Music college to MN Smarakam road (Model school junction to Mettukada Road ID -PWD -PH-4B - 142c) due to work carried out by smart city |
Project Code |
TVMSMARTCITY03229684 |
Type |
Main project |
Funding Agency |
SMARTCITY |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
Smart City |
Description |
Deposit work - Smart city Thiruvananthapuram Ltd - Reconstruction / maintenance of sewerage system from Music college to MN Smarakam road (Model school junction to Mettukada Road ID -PWD -PH-4B - 142c) due to work carried out by smart city |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kuriathy Sewerage Sn 2 |
AS Amount (Rs) |
4643300
|
AS Number |
KRFB/7686/2021-APE(Civil) |
TS Amount (Rs) |
4643300 |
TS Number |
23102/2021-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
19 Dec 2023 |
Coverage |
MN Smarakam road |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work - Smart city Thiruvananthapuram Ltd - Reconstruction / maintenance of sewerage system from Music college to MN Smarakam road (Model school junction to Mettukada Road ID -PWD -PH-4B - 142c) due to work carried out by smart city |
Kuriathy Sewerage Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Dec 2023 |
MH reconstruction work completed |
Kuriathy Sewerage Sn2 AE |
|
15 Dec 2023 |
MH reconstruction of 6th & 7th one in progress |
Kuriathy Sewerage Sn2 AE |
|
13 Dec 2023 |
MH reconstruction work of 3rd completed and 4th one in progress |
Kuriathy Sewerage Sn2 AE |
|
04 Dec 2023 |
1st Mh reconstruction work completed and the second MH reconstruction work in progress |
Kuriathy Sewerage Sn2 AE |
|
29 Nov 2023 |
As per the direction of SCTL, the work for MH reconstruction / new construction started |
Kuriathy Sewerage Sn2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
11/04/2022 |
Scheduled date of Completion of the Project |
10 Sep 2022 |
Expected date of Completion |
10/09/2022 |
Processing Dates
AS Date |
11 Mar 2022 |
TS Date |
16 Mar 2022 |