DEPOSIT-Pandalam Block Panchayath 2022-2023-Extension of pipeline - Kalyanikkalpadi - Paranthal Valiyathodu - Project No 25/23-.-Pipeline Work
| Project |
DEPOSIT-Pandalam Block Panchayath 2022-2023-Extension of pipeline - Kalyanikkalpadi - Paranthal Valiyathodu - Project No 25/23-.-Pipeline Work |
| Project Code |
PTADEPO012313642 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
DEPOSIT-Pandalam Block Panchayath 2022-2023-Extension of pipeline - Kalyanikkalpadi - Paranthal Valiyathodu - Project No 25/23-.-Pipeline Work |
| Status |
Completed |
| District |
Pathanamthitta |
| Executing Office |
Pathanamthitta Sn |
| AS Amount (Rs) |
542000
|
| AS Number |
No.B.25/2022 |
| TS Amount (Rs) |
542000 |
| TS Number |
TS/12235/2022_26_1_1 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
DEPOSIT-Pandalam Block Panchayath 2022-2023-Extension of pipeline - Kalyanikkalpadi - Paranthal Valiyathodu - Project No 25/23-.-Pipeline Work |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
DEPOSIT-Pandalam Block Panchayath 2022-2023-Extension of pipeline - Kalyanikkalpadi - Paranthal Valiyathodu - Project No 25/23-.-Pipeline Work |
Pathanamthitta Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 18 Apr 2023 |
Work 100% completed and bill submitted. |
Pathanamthitta PH Section - AE |
|
| 17 Apr 2023 |
Work 100% completed, bill under preparation. |
Pathanamthitta PH Section - AE |
|
| 13 Apr 2023 |
Work 100% completed. |
Pathanamthitta PH Section - AE |
|
| 13 Apr 2023 |
Work in progress, 80% of the work was completed. |
Pathanamthitta PH Section - AE |
|
| 12 Apr 2023 |
Work in progress, 60% of the work was completed. |
Pathanamthitta PH Section - AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
27/02/2023 |
| Scheduled date of Completion of the Project |
27 May 2023 |
| Expected date of Completion |
27/05/2023 |
Processing Dates
| AS Date |
21 Feb 2023 |
| TS Date |
25 Feb 2023 |