- Home
- Deposit work-2018-19-Athirappilly GP - P...
Deposit work-2018-19-Athirappilly GP - Providing Pressure filter and Platform for Kannankuzhy Jalanidhi Kudivella Padhathi
Project |
Deposit work-2018-19-Athirappilly GP - Providing Pressure filter and Platform for Kannankuzhy Jalanidhi Kudivella Padhathi |
Project Code |
TCRDEPO11207865 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work-2018-19-Athirappilly GP - Providing Pressure filter and Platform for Kannankuzhy Jalanidhi Kudivella Padhathi |
Status |
Completed |
District |
Thrissur |
Executing Office |
Chalakkudy PH Sn II |
AS Amount (Rs) |
450000
|
AS Number |
A2-364/2020 |
TS Amount (Rs) |
450000 |
TS Number |
1467/2021-2022 |
Total Bill Submitted (Rs) |
292515 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
400 |
Capacity in MLD |
0.24 |
Actual Project Completion Date |
31 May 2022 |
Coverage |
Kannankuzhy in Athirappilly GP |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work-2018-19-Athirappilly GP - Providing Pressure filter and Platform for Kannankuzhy Jalanidhi Kudivella Padhathi |
Chalakkudy PH Sn II |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Jul 2022 |
CC 1st and final bill submitted to division on 27.06.2022 |
Chalakudy AEE |
|
20 Jun 2022 |
Work completed CC first and final bill submitted to sub division on 18.06.2022 |
Chalakudy AE 2 |
|
04 Jun 2022 |
work completed on 31-05-2022 and bill under preparation |
Chalakudy AE 2 |
|
03 Jun 2022 |
work completed on 31-05-2022 and bill under preparation |
Chalakudy AE 2 |
|
02 Jun 2022 |
work completed on 31-05-2022 and bill under preparation |
Chalakudy AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
28/04/2021 |
Scheduled date of Completion of the Project |
06 Sep 2021 |
Expected date of Completion |
31/05/2022 |
Processing Dates
AS Date |
05 Nov 2020 |
TS Date |
28 Apr 2021 |