- Home
- DEPOSIT-2023-24 - Vengoor Grama panchaya...
DEPOSIT-2023-24 - Vengoor Grama panchayat - Public tap cutting-Disconnecting the existing Public taps in Various wards of Vengoor Grama Panchayat
Project |
DEPOSIT-2023-24 - Vengoor Grama panchayat - Public tap cutting-Disconnecting the existing Public taps in Various wards of Vengoor Grama Panchayat |
Project Code |
EKMDEPO102315229 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-2023-24 - Vengoor Grama panchayat - Public tap cutting-Disconnecting the existing Public taps in Various wards of Vengoor Grama Panchayat |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Aluva PH Dn |
AS Amount (Rs) |
270000
|
AS Number |
No-009489 dated 12/10/2023 |
TS Amount (Rs) |
270000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/14129/2022_26_1_1 Dated: 18-10-2023 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
7900 |
Capacity in MLD |
0.20 |
Actual Project Completion Date |
15 Jan 2024 |
Coverage |
Disconnecting the existing Public taps in Various wards of Vengoor Grama Panchayat |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-2023-24 - Vengoor Grama panchayat - Public tap cutting-Disconnecting the existing Public taps in Various wards of Vengoor Grama Panchayat |
Kuruppampady Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Mar 2024 |
Bill paid on 15.03.2024 |
Aluva PH Dn EE |
|
18 Jan 2024 |
148nos of public tap disconnected |
Perumbavoor AEE |
|
17 Jan 2024 |
148 nos public tap disconnected |
Perumbavoor AEE |
|
16 Jan 2024 |
142 Public tap had been disconnected. |
Kuruppampady AE |
|
15 Jan 2024 |
142 Public tap had been disconnected. |
Kuruppampady AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/11/2023 |
Scheduled date of Completion of the Project |
15 Jan 2024 |
Expected date of Completion |
15/01/2024 |
Processing Dates
AS Date |
12 Oct 2023 |
TS Date |
18 Oct 2023 |