Project | (JJM)-Phase II - UWSS to Anakkayam-JJM Phase II- Package 2aConstruction of 5.0 MLD WTP and allied works, 7.2 LL OHSR in Anakkayam Panchayath |
---|---|
Project Code | MLPJJM022216613P1 |
Type | Package |
Main Project | JJM phase II- UWSS to Anakkayam- Construction of 5MLD WTP, 7.2LL OHSR, Pumping main, pump sets and distribution systems. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | (JJM)-Phase II - UWSS to Anakkayam-JJM Phase II- Package 2aConstruction of 5.0 MLD WTP and allied works, 7.2 LL OHSR in Anakkayam Panchayath |
Status | On-going |
District | Malappuram |
Executing Office | Manjeri PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 80900000 |
TS Number | 11958/2023-2024 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/03/2024 |
---|---|
Scheduled date of Completion as per agreement | 15 Jun 2025 |
Expected date of Completion | 15/06/2025 |
TS Date | 15 Aug 2023 |
---|
Workorder Date | 15 Mar 2024 |
---|
Manjeri AE |
Date: 14/07/2025 |
Work in progress | 30% Completed
WORK IN PROGRESS.
Manjeri AE |
Date: 08/07/2025 |
Work in progress | 29% Completed
work in progress.