Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT WORK -Providing house hold service connection and line extension at Thrissur corporationsamboorna kudivella padhadhy--Divisions-,26,27,28,29,30,31- . 1405nos. FHTC-Providing house hold service connection and line extension

Project DEPOSIT WORK -Providing house hold service connection and line extension at Thrissur corporationsamboorna kudivella padhadhy--Divisions-,26,27,28,29,30,31- . 1405nos. FHTC-Providing house hold service connection and line extension
Project Code TCRDEPO112213521
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT WORK-Providing house hold service connection and line extension at Thrissur corporationsamboorna kudivella padhadhy--Divisions-,26,27,28,29,30,31- . 1405nos. FHTC-Providing house hold service connection and line extension
Status On-going
District Thrissur
Executing Office Ollur Sn
AS Amount (Rs) 34300000
AS Number WS1-10131/2022
TS Amount (Rs) 34300000
TS Number WRD/KWA-CE(CR)/EST/5703/2023,
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work -Pipe line Extension at Thrissur Corporation Samboorna Kudivella Padhadhy-Division 24 & 31-Pipe line work Ollur Sn
2 Deposit work -Pipe line Extension at Thrissur Corporation Samboorna Kudivella Padhadhy-Division 27 & amp ;28- Pipe line work Ollur Sn
3 Deposit work -Pipe line Extension at Thrissur Corporation Samboorna Kudivella Padhadhy-Division 29-Pipe line work Ollur Sn
4 Deposit work -Pipe line Extension at Thrissur Corporation Samboorna Kudivella Padhadhy-Division 30-Pipe line work Ollur Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Apr 2024 work completed Ollur AE
20 Mar 2024 WORK IN PROGRESS Ollur AE
24 Feb 2024 WORK IN PROGRESS Ollur AE
31 Jan 2024 WORK IN PROGRESS Ollur AE
25 Jan 2024 WORK IN PROGRESS Ollur AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/03/2023
Scheduled date of Completion of the Project 30 Jun 2023
Expected date of Completion 15/01/2024

Processing Dates

AS Date 04 Nov 2022
TS Date 09 Mar 2023

Other details

Project Officers View