Project |
AMRUT-2016-17 WSS to Guruvayur Municipality in Thrissur District - Construction of 10 LL OHSR and pumping main from WTP to OHSR at Savakotta, OHSR at office building & proposed OHSR at Chakkamkandam ( Revised AS -17.74 Cr) |
Project Code |
TCRGOI0917544 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Components:
1)Construction of 10 LL OHSR
2) Pumping main
CWPM from WTP to OHSR at Savakotta, OHSR at office building & proposed OHSR at Chakkamkandam
500mm DI - 1170m
400mm DI - 5770m
300mm DI - 2240m
|
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
177400000
|
AS Number |
GO(Rt) No. 3170/2017/LSGD |
TS Amount (Rs) |
151200000 |
TS Number |
TS/CE/CR/KWA/66/17-18 |
Total Bill Submitted (Rs) |
15077378 |
Total Bill Paid (Rs) |
12125378 |
Population Benefitted |
17854 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
31 Dec 2022 |
Coverage |
Thaikkad Zone of Guruvayoor Muncipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-2016-17 WSS to Guruvayur Municipality in Thrissur District - Construction of 10 LL OHSR and pumping main from WTP to OHSR at Savakotta, OHSR at office building & proposed OHSR |
Nattika Project Dn |
|
2 |
AMRUT 2017-18- WSS To Guruvayur Municipality in Thrissur District-construction of 10 LL capacity 0HSR at KWA Store compound |
Nattika Project Dn |
|
3 |
AMRUT - WSS to Guruvayur - Conveying and laying 500mm/400mm DI K9 CWPM in Chavakkad Wadakkanchery Road |
Nattika Project Dn |
|
4 |
AMRUT - WSS to Guruvayur - Conveying and layng 400mm DI K9 CWPM in Muthuvattur Guruvayur Road |
Nattika Project Dn |
|
5 |
AMRUT-WSS to Guruvayur Muncipality in Thrissur District-Clear water pumping main balance work(new route)- supplying and laying 500 mmDI pipe from Milan Auditorium to WTP site and 300 mm DI pipe from proposed OHSR Junction to office tank & 400 mm DI K9 pipe from Edappully Gandhi nagar road to proposed OHSR at Edappully jaram road500 mm DI pipe from Milan Auditorium to WTP site and 300 mm DI pipe from proposed |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
23 Feb 2024 |
10LL OHSR work completed. CWPM completed except one culvert crossing |
Nattika Project Dn |
|
20 Oct 2023 |
10LL OHSR work completed. CWPM completed except one culvert crossing at Edappully jaram road. |
Nattika Project Dn |
|
10 Oct 2023 |
10LL OHSR work completed. CWPM completed except one culvert crossing at Edappully jaram road. |
Nattika Project Dn |
|
27 Sep 2023 |
10LL OHSR work completed. CWPM completed except one culvert crossing at Edappully jaram road. |
Nattika Project Dn |
|
21 Sep 2023 |
10LL OHSR work completed. CWPM completed except one culvert crossing at Edappully jaram road. |
Nattika Project Dn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/04/2019 |
Scheduled date of Completion of the Project |
25 Feb 2020 |
Expected date of Completion |
31/07/2023 |
Processing Dates
AS Date |
28 Sep 2017 |
TS Date |
29 Jan 2018 |