State Plan - 2016-17- T S S - Construction of Manholes and laying 150 mm SW sewer line from Pattom Marapalam Road near Balasubramaniya temple lane,Iswarya lane and Bund road
Project |
State Plan - 2016-17- T S S - Construction of Manholes and laying 150 mm SW sewer line from Pattom Marapalam Road near Balasubramaniya temple lane,Iswarya lane and Bund road |
Project Code |
TVMGOK11161756 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State Plan - 2016-17- T S S - Construction of Manholes and laying 150 mm SW sewer line from Pattom Marapalam Road near Balasubramaniya temple lane,Iswarya lane and Bund road.
AS-G.O.(Rt.) No. 892/2016/WRD dated 16.11.2016
Laying of new sewer line in 3 lanes near marapalam ,Pattom. |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Sasthamangalam Sewerage Sn |
AS Amount (Rs) |
2105000
|
AS Number |
892/2016 |
TS Amount (Rs) |
1883000 |
TS Number |
2953/2018-2019 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
150 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
24 May 2022 |
Coverage |
Laying of new sewer line in 3 lanes near marapalam ,Pattom. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan - 2016-17- T S S - Construction of Manholes and laying 150 mm SW sewer line from Pattom Marapalam Road near Balasubramaniya temple lane,Iswarya lane and Bund road |
Sasthamangalam Sewerage Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 May 2022 |
Work completed |
Sasthamangalam Sewerage Sn AE |
|
20 May 2022 |
interlock relaying progress |
Sasthamangalam Sewerage Sn AE |
|
20 May 2022 |
work stopped due to rain |
Sasthamangalam Sewerage Sn AE |
|
17 May 2022 |
work stopped due to rain |
Sasthamangalam Sewerage Sn AE |
|
14 May 2022 |
work stopped due to rain |
Sasthamangalam Sewerage Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/01/2022 |
Scheduled date of Completion of the Project |
31 Mar 2022 |
Expected date of Completion |
31/05/2022 |
Processing Dates
AS Date |
16 Nov 2016 |
TS Date |
20 Oct 2018 |