DW-Improving water supply to Kochi Corporation Div 49 (old) at Njanewara lane 63 mm PVC pipe at Parayil road 110 mm PVC pipe .

Project DW-Improving water supply to Kochi Corporation Div 49 (old) at Njanewara lane 63 mm PVC pipe at Parayil road 110 mm PVC pipe .
Project Code EKMDEPO11218809
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DW-Improving water supply to Kochi Corporation Div 49 (old) at Njanewara lane 63 mm PVC pipe at Parayil road 110 mm PVC pipe.
Status Completed
District Ernakulam
Executing Office Kaloor Sub Dn 2
AS Amount (Rs) 630000
AS Number TS_MAINTENANCE/2019/10176
TS Amount (Rs) 630000
TS Number TS/2021-2022/2019/10176
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 17791
Capacity in MLD 0.25
Actual Project Completion Date 10 Feb 2023
Coverage DW-Improving water supply to Kochi Corporation Div 49 (old) at Njanewara lane 63 mm PVC pipe at Parayil road 110 mm PVC pipe.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DW-Improving water supply to Kochi Corporation Div 49 (old) at Njanewara lane 63 mm PVC pipe Kaloor WW Sn 2
2 DW-Improving water supply to Kochi Corporation Div 49 (old) at Parayil road 110 mm PVC pipe . Kaloor WW Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Apr 2024 Bill submitted Kaloor AE 2
19 Apr 2024 Bill submitted Kaloor AE 2
23 Mar 2024 Bill submitted Kaloor AE 2
06 Mar 2024 Bill submitted Kaloor AE 2
21 Feb 2024 Bill submitted Kaloor AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/02/2022
Scheduled date of Completion of the Project 09 Mar 2022
Expected date of Completion 28/02/2023

Processing Dates

AS Date 16 Nov 2021
TS Date 16 Nov 2021

Other details

Project Officers View