- Home
- Deposit work of Elampalloor grama pancha...
Deposit work of Elampalloor grama panchayth-2021-22 Annual plan-Project no.218/22-Pipe line extension in various wards of Elampalloor panchayth
Project |
Deposit work of Elampalloor grama panchayth-2021-22 Annual plan-Project no.218/22-Pipe line extension in various wards of Elampalloor panchayth |
Project Code |
KLMDEPO032210895 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work of Elampalloor grama panchayth-2021-22 Annual plan-Project no.218/22-Pipe line extension in various wards of Elampalloor panchayth |
Status |
Completed |
District |
Kollam |
Executing Office |
Kundara PH Sn |
AS Amount (Rs) |
4202000
|
AS Number |
1(9) |
TS Amount (Rs) |
4202000 |
TS Number |
275/2022-23 |
Total Bill Submitted (Rs) |
3021270 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
10000 |
Capacity in MLD |
0.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
50% |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Elampalloor grama panchayth-2021-22 Annual plan-Project no.218/22-Pipe line extension in various wards of Elampalloor panchayth |
Kundara PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Nov 2022 |
Completed |
Kundara PH Sn - AE |
|
07 Oct 2022 |
Work in Progress |
Kundara PH Sn - AE |
|
16 Sep 2022 |
work on progress |
Kottarakkara PH Dn EE |
|
01 Sep 2022 |
Pipe Laying Work In Progress |
Kottarakkara PH Dn EE |
|
30 Aug 2022 |
Agreement executed |
Kottarakkara PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/05/2022 |
Scheduled date of Completion of the Project |
17 Aug 2022 |
Expected date of Completion |
17/08/2022 |
Processing Dates
AS Date |
27 Mar 2022 |
TS Date |
06 Apr 2022 |