JAL JEEVAN MISSION-2021-2022- WSS TO PAMPADY PANCHAYAT KOTTAYAM DISTRICT

Project JAL JEEVAN MISSION-2021-2022- WSS TO PAMPADY PANCHAYAT KOTTAYAM DISTRICT
Project Code KTMJJM09218534
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description In this proposal supplying and laying of 250mm DI K9 CW branched PM 4.5 km from 8 Mile to the proposed 8.5LL capacity GLSR with single stage at Pothenpuram,from which the treated water treated water is proposed to be distributed to Zone 2 of the Panchayath area. 126km new distribution pipe lines with 300mm to 200mm DI pipes & 160mm to 63mm PVC/ HDPE pipes is proposed for Zone 1. 98km new distribution pipe lines with 300mm to 200mm DI pipes & 160mm to 63mm PVC /HDPE pipes is proposed for Zone 2. Supply and erection of pump sets for pumping clear water to RIT and Pothenpram thanks were also proposed through this project.Provision is made for giving 8000 FHTCs through this proposal.
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 481330000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 200600000
TS Number TS/2021-2022/2021/40023
Total Bill Submitted (Rs) 97047415
Total Bill Paid (Rs) 97047415
Population Benefitted 40153
Capacity in MLD 6.00
Actual Project Completion Date 28 Feb 2023
Coverage PAMPADY
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Package 1,2,3&9-SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC'S IN ZONE 1-RIT PAMPADY-POTHENPURAM Kottayam Project Dn
2 Package 4- SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC'S IN ZONE 1-RIT PAMPADY - PANGADA AREA Kottayam Project Dn
3 Package 5 - SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC'S IN ZONE 1-RIT PAMPADY- MEENADOM AREA Kottayam Project Dn
4 Package 6- SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC'S IN ZONE 1-RIT PAMPADY- KOOROPADA AREA Kottayam Project Dn
5 Package 7 -SUPPLYING AND LAYING DI/PVC/GI DISTRIBUTION NETWORK AND PROVIDING FHTC'S IN ZONE 1-RIT PAMPADY-SOUTH PAMPADY AREA Kottayam Project Dn
6 Package 8-SUPPLYING,ERECTING AND COMMISSIONING OF CLEAR WATER PUMP SETS-RIT PAMPADY-POTHENPURAM Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Jan 2024 192km laid out of 229km.6132connections given out of 8000 connections. Kottayam AE 3
27 Jul 2022 Meeting at Pampady panchayath was held on 18.7.2022.Panchayath authorities KWA AE,ISA and JJM staffs attended the meeting to discuss the progress and issues in on going JJM works. Kottayam AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/01/2022
Scheduled date of Completion of the Project 28 Feb 2023
Expected date of Completion 30/04/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 15 Dec 2021

Other details