- Home
- Deposit Work - Kottarakkara Block Pt. 20...
Deposit Work - Kottarakkara Block Pt. 2021-22 - Providing Pipe line extension and Water connection to Zeneth mukku S C colony in Kareepra Grama Pt
Project |
Deposit Work - Kottarakkara Block Pt. 2021-22 - Providing Pipe line extension and Water connection to Zeneth mukku S C colony in Kareepra Grama Pt |
Project Code |
KLMDEPO022210259 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Providing Pipe line extension and Water connection to Zeneth mukku S C colony in Kareepra Grama Pt |
Status |
Completed |
District |
Kollam |
Executing Office |
Kundara PH Sn |
AS Amount (Rs) |
1757300
|
AS Number |
KB1 - 2318/2021 |
TS Amount (Rs) |
1748000 |
TS Number |
22442/2021-22 |
Total Bill Submitted (Rs) |
811526 |
Total Bill Paid (Rs) |
811526 |
Population Benefitted |
350 |
Capacity in MLD |
3.00 |
Actual Project Completion Date |
03 Jun 2022 |
Coverage |
Zeneth mukku S C colony in Kareepra Grama Pt |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit Work - Kottarakkara Block Pt. 2021-22 - Providing Pipe line extension and Water connection to Zeneth mukku S C colony in Kareepra Grama Pt |
Kundara PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Sep 2022 |
completed |
Kundara PH Sn - AE |
|
16 Sep 2022 |
completed |
Kottarakkara PH Dn EE |
|
01 Sep 2022 |
Work in progress |
Kottarakkara PH Dn EE |
|
30 Aug 2022 |
Work In Progress |
Kottarakkara PH Dn EE |
|
28 Aug 2022 |
work in progress |
Kottarakkara PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/04/2022 |
Scheduled date of Completion of the Project |
03 Jun 2022 |
Expected date of Completion |
03/06/2022 |
Processing Dates
AS Date |
02 Feb 2022 |
TS Date |
09 Mar 2022 |