Jal Jeevan Mission - 2020-21 - Phase II - Providing FHTCs in (3446 nos) and pipeline extension to Kuthanur Gramapanchayath
Project |
Jal Jeevan Mission - 2020-21 - Phase II - Providing FHTCs in (3446 nos) and pipeline extension to Kuthanur Gramapanchayath |
Project Code |
PKDJJM12207546 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission - 2020-21 - Phase II - Providing FHTCs in (3446 nos) and pipeline extension to Kuthanur Gramapanchayath |
Status |
Completed |
District |
Palakkad |
Executing Office |
Kuzhalmannam Sn |
AS Amount (Rs) |
35000000
|
AS Number |
GO(Rt)No 777/2020/WRD |
TS Amount (Rs) |
33400000 |
TS Number |
TS/2020-21/2020/21376 |
Total Bill Submitted (Rs) |
27879431 |
Total Bill Paid (Rs) |
27879431 |
Population Benefitted |
13500 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
31 Aug 2022 |
Coverage |
Kuthanur Gramapanchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission - 2020-21 - Phase II - Providing FHTCs in (3446 nos) and pipeline extension to Kuthanur Gramapanchayath |
Kuzhalmannam Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Dec 2022 |
work in progress |
Kuzhalmannam PH Sn AE |
|
22 Dec 2022 |
2389/3446 , WORK IN PROGRESS |
Kuzhalmannam PH Sn AE |
|
12 Sep 2022 |
2018/3451 |
Kuzhalmannam PH Sn AE |
|
05 Sep 2022 |
2018/3451 |
Kuzhalmannam PH Sn AE |
|
29 Aug 2022 |
2011/3451 |
Kuzhalmannam PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/02/2021 |
Scheduled date of Completion of the Project |
25 Jun 2021 |
Expected date of Completion |
31/12/2022 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
11 Jan 2021 |