Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KCH-WS-02B:- Water Supply improvements to Vennala and Elamakkara

Project KCH-WS-02B:- Water Supply improvements to Vennala and Elamakkara
Project Code EKMADB07113008P4
Type Package
Main Project ADB Assisted KSUDP Water Supply Scheme
Funding Agency ADB
Category ADB assisted KSUD Project
Type of scheme Water Supply
Scheme
Description Water Supply improvements to Vennala and Elamakkara
Status Completed
District Ernakulam
Executing Office Kochi Project Division
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Water Supply improvements to Vennala and Elamakkara

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/12/2011
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 23/03/2013

Processing Dates

Tender Closing 03 Feb 2011

Approval Dates

Workorder Date 09 Nov 2011
NA 08 Dec 2011

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kochi WS Project Dn AEE-2
Date: 09/09/2020

Work has been completed | 100% Completed

Work completed.