Deposit work-2020-21-KWA-MCH-PIPMS-Deposit work: Providing additional PVC Storage tank and erecting submersible motor and allied works for PIPMS institute at Medical college campus etc complete.
| Project |
Deposit work-2020-21-KWA-MCH-PIPMS-Deposit work: Providing additional PVC Storage tank and erecting submersible motor and allied works for PIPMS institute at Medical college campus etc complete. |
| Project Code |
TVMGOK08206041P20 |
| Type |
Package |
| Main Project |
Deposit Work-2020-21-KWA Medical college
|
| Funding Agency |
GOK |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
KWA-MCH-PIPMS-Deposit work: Providing additional PVC Storage tank and erecting submersible motor and allied works for PIPMS institute at Medical college campus etc complete. |
| Status |
On-going |
| District |
Thiruvananthapuram |
| Executing Office |
TVM Medical College Sn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
360000 |
| TS Number |
14886/2020-2021 |
| Technical specification |
Providing additional PVC Storage tank and erecting submersible motor and allied works for PIPMS institute at Medical college campus etc complete. |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
26/02/2021 |
| Scheduled date of Completion as per agreement |
25 Mar 2021 |
| Expected date of Completion |
01/05/2021 |
Processing Dates
| TS Date |
19 Jan 2021 |
| Estimate Approval |
19 Jan 2021 |
| NIT Approval |
27 Jan 2021 |
| Tender Closing |
24 Feb 2021 |
| Price bid opening |
26 Feb 2021 |
Approval Dates
| Workorder Date |
26 Feb 2021 |
| NA |
15 Mar 2021 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Thiruvananthapuram - Med col - AE |
| Date: 21/10/2021 |
Work has been completed | 100% Completed
Work Completed
.
| Thiruvananthapuram - Med col - AE |
| Date: 18/10/2021 |
Work has been completed | 100% Completed
Work Completed.