DAWSS to Edappal & adj.pts laying 110 mm DI pipes in kuttipuram -Edappal road at Thangalpadi wher the existing 110mm PVC pipes are exposed in road level for a length of 125mtrs.
DAWSS to Edappal & adj.pts laying 110 mm DI pipes in kuttipuram -Edappal road at Thangalpadi wher the existing 110mm PVC pipes are exposed in road level for a length of 125mtrs.
Project Code
MLPGOK06217978
Type
Main project
Funding Agency
GOK
Category
State plan
Type of scheme
Water Supply
Scheme
2215-02-106-97
Description
DAWSS to Edappal & adj.pts laying 110 mm DI pipes in kuttipuram -Edappal road at Thangalpadi wher the existing 110mm PVC pipes are exposed in road level for a length of 125mtrs.
Status
Dropped
District
Malappuram
Executing Office
Edappal PH Dn
AS Amount (Rs)
500000
AS Number
KWA/JB/PIU-1/AE-4/State plan /OPT/05/2021-22 (IX)
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
0.10
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
DAWSS to Edappal & adj.pts laying 110 mm DI pipes in kuttipuram -Edappal road at Thangalpadi wher the existing 110mm PVC pipes are exposed in road level for a length of 125mtrs.
Edappal Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
23 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE
12 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE
05 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE
03 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE
01 Aug 2022
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan