KIIFB-UWSS to Muvattupuzha-Replacing existing pipelines due to widening of MC road from Post Office Junction to Velloorkunnam signal using 300mm DI K9, 200mm DI K9, 150mm DI K9, 100mm DI K9, 160mm PVC, 110mm PVC and 90mm PVC pipes-Pipeline Work
Project |
KIIFB-UWSS to Muvattupuzha-Replacing existing pipelines due to widening of MC road from Post Office Junction to Velloorkunnam signal using 300mm DI K9, 200mm DI K9, 150mm DI K9, 100mm DI K9, 160mm PVC, 110mm PVC and 90mm PVC pipes-Pipeline Work |
Project Code |
EKMKIIFB022115218 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB-UWSS to Muvattupuzha-Replacing existing pipelines due to widening of MC road from Post Office Junction to Velloorkunnam signal using 300mm DI K9, 200mm DI K9, 150mm DI K9, 100mm DI K9, 160mm PVC, 110mm PVC and 90mm PVC pipes-Pipeline Work |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Muvattupuzha PH Dn |
AS Amount (Rs) |
27500000
|
AS Number |
KRFB-PMU/MVPA-IDK/MVPA-PO/2021 dated 24/02/2021 |
TS Amount (Rs) |
19500000 |
TS Number |
TS/11693/2022_26_1_1/RC 1 dated 04/04/2023 Reg No.290/2023-2024 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
200 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Replacing existing pipelines due to widening of MC road from Post Office Junction to Velloorkunnam signal using 300mm DI K9, 200mm DI K9, 150mm DI K9, 100mm DI K9, 160mm PVC, 110mm PVC and 90mm PVC pipes |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB-UWSS to Muvattupuzha-Replacing existing pipelines due to widening of MC road from Post Office Junction to Velloorkunnam signal using 300mm DI K9, 200mm DI K9, 150mm DI K9, 100mm DI K9, 160mm PVC, 110mm PVC and 90mm PVC pipes-Pipeline Work |
Muvattupuzha PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 May 2024 |
agreement executed |
Muvattupuzha PH Section - AE |
|
02 May 2024 |
agreement executed |
Muvattupuzha PH Section - AE |
|
25 Apr 2024 |
agreement executed |
Muvattupuzha PH Section - AE |
|
20 Apr 2024 |
agreement executed |
Muvattupuzha PH Section - AE |
|
16 Apr 2024 |
agreement executed |
Muvattupuzha PH Section - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
21/09/2023 |
Scheduled date of Completion of the Project |
20 Apr 2024 |
Expected date of Completion |
20/04/2024 |
Processing Dates
AS Date |
24 Feb 2021 |
TS Date |
04 Apr 2023 |