Jal Jeevan Mission (JJM)-JJM - Retrofittable / Extendable - Providing household water service connections in Ramankari Panchayath in Alappuzha District

Project Jal Jeevan Mission (JJM)-JJM - Retrofittable / Extendable - Providing household water service connections in Ramankari Panchayath in Alappuzha District
Project Code ALPJJM092215529P1
Type Package
Main Project Jal Jeevan Mission (JJM)-JJM - Retrofittable / Extendable - Providing household water service connections in Ramankari Panchayath in Alappuzha District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM - Retrofittable / Extendable - Providing household water service connections in Ramankari Panchayath in Alappuzha District
Status On-going
District Alappuzha
Executing Office KIIFB Projects (ALP)
Agreement Number
Agreement Date
TS Amount (Rs) 40910000
TS Number WRD/KWA/CE(CR)/EST- TS/3046/2022
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 10 Jan 2024
Expected date of Completion Date is not specified

Processing Dates

TS Date 22 Sep 2022
Estimate Approval 22 Sep 2022

Approval Dates

Workorder Date 05 Jul 2023
NA 15 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha KIIFB - AE 4
Date: 18/05/2024

Work in progress | 2% Completed

Pipe supplied 90mm HDPE 7600 m. Laying started. Total laid length of 90mm HDPE - 3712m. Total no. of FHTC given- 51 Nos..

Alappuzha KIIFB - AE 4
Date: 17/05/2024

Work in progress | 2% Completed

Pipe supplied 90mm HDPE 7600 m. Laying started. Total laid length of 90mm HDPE - 3712m. Total no. of FHTC given- 51 Nos..