Aug of Uwss to Chengannur - Replacing 250mm MS pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office).

Project Aug of Uwss to Chengannur - Replacing 250mm MS pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office).
Project Code ALPDEPO03217072
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Aug of Uwss to Chengannur - Replacing 250mm MS pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office).
Status Completed
District Alappuzha
Executing Office Alappuzha PH Dn
AS Amount (Rs) 820000
AS Number 1000157/2020/10701
TS Amount (Rs) 820000
TS Number TS/2021-2022/2021/7921
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 2500
Capacity in MLD 1.00
Actual Project Completion Date 30 Mar 2022
Coverage 50 % Of Chengannur Muncipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Aug of Uwss to Chengannur - Replacing 250mm MS pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office). Chengannur WS Sn
2 Realigning 250 mm M S pipe line Temporarily with 160 mm PVC pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office). Chengannur WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Apr 2022 Work completed Chengannur PH Sn AE
22 Mar 2022 Work completed Chengannur PH Sn AE
17 Mar 2022 250mm MS Pipeline work in progress Chengannur PH Sn AE
14 Mar 2022 250mm MS Pipeline work in progress Chengannur PH Sn AE
11 Mar 2022 Temporary arrangement with 160mm PVC pipe was completed, Realigning MS pipe can be done only after completing the construction of new bridge, expected date of completion is 15/03/2022 Chengannur PH Sn AE

Project Review

See All Review messages
Review Date Review Message Review Attended By
07 Jul 2021 Data / Date not entered. Photos not added . Do it immediately EE

Duration & Sanction dates

Date of start of Project 11/05/2021
Scheduled date of Completion of the Project 30 Nov 2021
Expected date of Completion 30/03/2022

Processing Dates

AS Date 01 Mar 2021
TS Date 15 Mar 2021

Other details