Project | Aug of Uwss to Chengannur - Replacing 250mm MS pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office). |
---|---|
Project Code | ALPDEPO03217072 |
Type | Main project |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Aug of Uwss to Chengannur - Replacing 250mm MS pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office). |
Status | Completed |
District | Alappuzha |
Executing Office | Alappuzha PH Dn |
AS Amount (Rs) | 820000 |
AS Number | 1000157/2020/10701 |
TS Amount (Rs) | 820000 |
TS Number | TS/2021-2022/2021/7921 |
Total Bill Submitted (Rs) | 0 |
Total Bill Paid (Rs) | 0 |
Population Benefitted | 2500 |
Capacity in MLD | 1.00 |
Actual Project Completion Date | 30 Mar 2022 |
Coverage | 50 % Of Chengannur Muncipality |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | Aug of Uwss to Chengannur - Replacing 250mm MS pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office). | Chengannur WS Sn | |
2 | Realigning 250 mm M S pipe line Temporarily with 160 mm PVC pipe for the widening of Puthencavu bridge by PWD in Chenganuur Muncipality (East of Excises Office). | Chengannur WS Sn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Apr 2022 | Work completed | Chengannur PH Sn AE | |
22 Mar 2022 | Work completed | Chengannur PH Sn AE | |
17 Mar 2022 | 250mm MS Pipeline work in progress | Chengannur PH Sn AE | |
14 Mar 2022 | 250mm MS Pipeline work in progress | Chengannur PH Sn AE | |
11 Mar 2022 | Temporary arrangement with 160mm PVC pipe was completed, Realigning MS pipe can be done only after completing the construction of new bridge, expected date of completion is 15/03/2022 | Chengannur PH Sn AE |
Review Date | Review Message | Review Attended By |
---|---|---|
07 Jul 2021 | Data / Date not entered. Photos not added . Do it immediately | EE |
Date of start of Project | 11/05/2021 |
---|---|
Scheduled date of Completion of the Project | 30 Nov 2021 |
Expected date of Completion | 30/03/2022 |
AS Date | 01 Mar 2021 |
---|---|
TS Date | 15 Mar 2021 |
Project Officers | View |
---|