JJM- ANCHAL Grama Panchayath

Project JJM- ANCHAL Grama Panchayath
Project Code KLMJJM08203263
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description in ANCHAL Grama Panchayath From Existing Scheme and Extension during the period 2020-21 with
Status On-going
District Kollam
Executing Office Valakom PH Sub Dn
AS Amount (Rs) 217459000
AS Number G.O.(Rt)No.541/2020/WRD
TS Amount (Rs) 160700000
TS Number TS/2020-2021/2020/16495
Total Bill Submitted (Rs) 121459041
Total Bill Paid (Rs) 121459041
Population Benefitted 33088
Capacity in MLD 2.20
Actual Project Completion Date 08 Feb 2024
Coverage Anchal Grama panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Additional pipe laying for last mile connectivity and supply and erection of 5HP CF pump set at Anchal OHSR for supplying water to high elevated areas at Pinnacle view point Panamkuttimala HW Sn
2 JJM Anchal phase II- JICA gap closing work and extension of pipe line for additional coverage of Anchal gp Panamkuttimala HW Sn
3 JJM-Estimate for providing FHTC In ANCHAL Grama Panchayath From Existing Scheme and Extension during the period 2020-21 Madathara Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Apr 2024 Total geotagged connection 6840.package 1 completed Valakom Sub Dn AEE
26 Feb 2024 Total geotagged connection 6840.package 1 completed Valakom Sub Dn AEE
24 Feb 2024 Total geotagged connection 6840.package 1 completed Valakom Sub Dn AEE
22 Feb 2024 Total geotagged connection 6840.package 1 completed Panamkuttimala HW AE
19 Feb 2024 Total geotagged connection 6840.package 1 completed Valakom Sub Dn AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/02/2021
Scheduled date of Completion of the Project 09 Feb 2022
Expected date of Completion 31/03/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 12 Sep 2020