MLA SDF - 2020 - 21 - TSS - Thiruvananthapuram Constituency - Increasing the capacity of 150 mm Dia line SW pipe in Friends nagar residence association no. FNA 20 to 39
Project |
MLA SDF - 2020 - 21 - TSS - Thiruvananthapuram Constituency - Increasing the capacity of 150 mm Dia line SW pipe in Friends nagar residence association no. FNA 20 to 39 |
Project Code |
TVMDC-LAC/ADS/SDF/KSCADC11205767 |
Type |
Main project |
Funding Agency |
DC-LAC/ADS/SDF/KSCADC |
Category |
MLA SDF |
Type of scheme |
Water Supply |
Scheme |
DC-LAC/ADS/SDF/KSCADC |
Description |
Increasing the capacity of 150 mm Dia line SW pipe in Friends nagar residence association no. FNA 20 to 39
|
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kuriathy Sewerage Sn 1 |
AS Amount (Rs) |
421000
|
AS Number |
D1-3117/20 |
TS Amount (Rs) |
421000 |
TS Number |
11040/2020-2021 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
29 Jul 2021 |
Coverage |
Rehabilitation of existing sewer network in friends nagar in Chalai ward. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
MLA SDF - 2020 - 21 - TSS - Thiruvananthapuram Constituency - Increasing the capacity of 150 mm Dia line SW pipe in Friends nagar residence association no. FNA 20 to 39 |
Kuriathy Sewerage Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Jul 2021 |
Work completed. |
Kuriathy Sewerage Sn1 AE |
|
26 Jul 2021 |
96% : 60/60 M pipe laying and 7/7 MH construction completed, Restoration concrete pending, clearing and compacting of ground prior to restoration in progress. Concrete delayed due to rain. Scheduled for this week. |
Kuriathy Sewerage Sn1 AE |
|
23 Jul 2021 |
96% : 60/60 M pipe laying and 7/7 MH construction completed, Restoration concrete pending, clearing and compacting of ground prior to restoration in progress. Concrete delayed due to rain. Scheduled for next week due to rain. |
Kuriathy Sewerage Sn1 AE |
|
20 Jul 2021 |
96% : 60/60 M pipe laying and 7/7 MH construction completed, Restoration concrete pending, clearing and compacting of ground prior to restoration in progress. Concrete delayed due to rain. Scheduled on 22/07/2021. |
Kuriathy Sewerage Sn1 AE |
|
17 Jul 2021 |
96% : 60/60 M pipe laying and 7/7 MH construction completed, Restoration concrete pending, clearing and compacting of ground prior to restoration in progress. Concrete delayed due to rain. Scheduled on 21/07/2021. |
Kuriathy Sewerage Sn1 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/04/2021 |
Scheduled date of Completion of the Project |
14 Jun 2021 |
Expected date of Completion |
28/07/2021 |
Processing Dates
AS Date |
05 Nov 2020 |
TS Date |
18 Nov 2020 |