Rebuild Kerala Initiative (RKI)- Project of "Providing additional facility to treat septage in 3 MLD Septage Treatment Plant (STP) of Guruvayoor Sewerage Scheme at Chakkumkandam" - Construction of dilution tank &allied works"

Project Rebuild Kerala Initiative (RKI)- Project of "Providing additional facility to treat septage in 3 MLD Septage Treatment Plant (STP) of Guruvayoor Sewerage Scheme at Chakkumkandam" - Construction of dilution tank &allied works"
Project Code TCRRKI062211830
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Rebuild Kerala Initiative (RKI)- Project of "Providing additional facility to treat septage in 3 MLD Septage Treatment Plant (STP) of Guruvayoor Sewerage Scheme at Chakkumkandam" - Construction of dilution tank &allied works"
Status Completed
District Thrissur
Executing Office Guruvayur PH Sn
AS Amount (Rs) 3600000
AS Number KWA/JB/P1/675/2015-16/Part -1/Vol II
TS Amount (Rs) 3600000
TS Number WRD/KWA-CEP/EST_TS/356/2022_5_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 2000
Capacity in MLD 0.50
Actual Project Completion Date 31 May 2023
Coverage 0.5

Packages

No. Project Name Location View
1 Rebuild Kerala Initiative (RKI)- Project of "Providing additional facility to treat septage in 3 MLD Septage Treatment Plant (STP) of Guruvayoor Sewerage Scheme at Chakkumkandam" - Construction of dilution tank &allied works" Guruvayur PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Nov 2023 Revised Estimate submitted to SE for Approval on 17.10.2023 Thrissur PH Dn EE
10 Nov 2023 Revised Estimate submitted to SE for Approval on 17.10.2023 Thrissur PH Dn EE
06 Nov 2023 Revised Estimate submitted to SE for Approval on 17.10.2023 Thrissur PH Dn EE
02 Nov 2023 Revised Estimate submitted to SE for Approval on 17.10.2023 Thrissur PH Dn EE
25 Oct 2023 Revised Estimate submitted to SE for Approval on 17.10.2023 Thrissur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/02/2023
Scheduled date of Completion of the Project 30 Jun 2023
Expected date of Completion 31/05/2023

Processing Dates

AS Date 27 Jun 2022
TS Date 22 Jul 2022

Other details

Project Officers View