Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020-2021-Phase I - RWSS to Vythiri -Providing Retrofitting/extandable Functional Household Connection Vythiri grama Panchayat

Project JJM 2020-2021-Phase I - RWSS to Vythiri -Providing Retrofitting/extandable Functional Household Connection Vythiri grama Panchayat
Project Code WYDJJM08202811
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Intake well – Existing Pumping System – Existing Transmission Lines – Existing Water Treatment Plants – Existing O H Tanks – Existing G L Tank- Existing Supply lines – 20 mm PVC - 4500 m Distribution Lines – 63 mm PVC - 750 m/ 75 mm PVC- 800 m/110 mm PVC - 2000 m/ GI pipe 40 mm/50mm/65 mm 80 mm /100mm - 400m/500 m/300 m/100 m/ 550m Quantity of water to be Produced – NA Expected annual revenue when project is completed – NA Ratio of material and Labor – Total cost of the project - 141.00 Lakhs
Status Completed
District Wayanad
Executing Office Sulthan Bathery PH Dn
AS Amount (Rs) 14100000
AS Number GO(Rt) 541/2020/WRD
TS Amount (Rs) 14100000
TS Number TS/2020-2021/2020/19185
Total Bill Submitted (Rs) 2723683
Total Bill Paid (Rs) 1404094
Population Benefitted 2250
Capacity in MLD 0.35
Actual Project Completion Date 31 Dec 2021
Coverage Functional house hold connections 450 nos
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 2020-2021-Phase I - RWSS to Vythiri -Providing Retrofitting/extandable Functional Household Connection Vythiri grama Panchayat Kalpetta PH Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Dec 2021 work is completed Sulthan Bathery PH Dn EE
01 Dec 2021 FHTC Work completed,Tank Work in Final Stage Sulthan Bathery PH Dn EE
23 Nov 2021 FHTC Work completed,Tank Work in Final Stage Sulthan Bathery PH Dn EE
20 Nov 2021 work slow progress, asked contractor to complete last finishing works. Sulthan Bathery PH Dn EE
08 Nov 2021 Tank painting only pending, due to heavy rain work progress slowly. Sulthan Bathery PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/08/2020
Scheduled date of Completion of the Project 22 Apr 2021
Expected date of Completion 30/12/2021

Processing Dates

AS Date 21 Aug 2020
TS Date 27 Aug 2020

Other details

Project Officers View