State Plan 2022-23 - Replacement of existing 150mm AC line along Chackai - Karali aatuvarambu Road having frequent leaks after laying of 600mm DI Sewerage Pumping main under W W Section Pattoor

Project State Plan 2022-23 - Replacement of existing 150mm AC line along Chackai - Karali aatuvarambu Road having frequent leaks after laying of 600mm DI Sewerage Pumping main under W W Section Pattoor
Project Code TVMGOK052211414
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2022-23 - Replacement of existing 150mm AC line along Chackai - Karali aatuvarambu Road having frequent leaks after laying of 600mm DI Sewerage Pumping main under W W Section Pattoor
Status Completed
District Thiruvananthapuram
Executing Office Pattoor Sn(Maintenance)
AS Amount (Rs) 7300000
AS Number KWA/JB/PIU1/AE1/22
TS Amount (Rs) 6579000
TS Number 5045/2022-23
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 1500
Capacity in MLD 1.00
Actual Project Completion Date Date is not specified
Coverage Replacement of existing 150mm AC line along Chackai - Karali aatuvarambu Road having frequent leaks after laying of 600mm DI Sewerage Pumping main under W W Section Pattoor
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2022-23 - Replacement of existing 150mm AC line along Chackai - Karali aatuvarambu Road having frequent leaks after laying of 600mm DI Sewerage Pumping main under W W Section Pattoor Pattoor Sn(Maintenance)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Jul 2023 Work completed. Thiruvananthapuram PH Dn (N) - EE
18 Aug 2022 Only single participant. Pattoor WW Sn AE
10 Aug 2022 Work re-tendered on 06.07.2022. single participant Pattoor WW Sn AE
03 Aug 2022 Work re-tendered on 06.07.2022. single participant Pattoor WW Sn AE
30 Jul 2022 Work re-tendered on 06.07.2022. single participant Pattoor WW Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/09/2022
Scheduled date of Completion of the Project 20 Mar 2023
Expected date of Completion 20/03/2023

Processing Dates

AS Date 11 May 2022
TS Date 30 May 2022

Other details

Project Officers View