DEPOSIT- PWD - Rebuilding of Naranath Bridge - Shifting of KWA utilities-Shifting of KWA pipe line on Naranath Bridge-Pipeline Work

Project DEPOSIT- PWD - Rebuilding of Naranath Bridge - Shifting of KWA utilities-Shifting of KWA pipe line on Naranath Bridge-Pipeline Work
Project Code KNRDEPO022415906P1
Type Package
Main Project DEPOSIT- PWD - Rebuilding of Naranath Bridge - Shifting of KWA utilities-Shifting of KWA pipe line on Naranath Bridge-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT- PWD - Rebuilding of Naranath Bridge - Shifting of KWA utilities-Shifting of KWA pipe line on Naranath Bridge-Pipeline Work
Status On-going
District Kannur
Executing Office Kannur WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 1280000
TS Number 27443/2023-2024
Technical specification DEPOSIT- PWD - Rebuilding of Naranath Bridge - Shifting of KWA utilities-Shifting of KWA pipe line on Naranath Bridge-Pipeline Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 02/05/2024
Scheduled date of Completion as per agreement 31 May 2024
Expected date of Completion 31/05/2025

Processing Dates

TS Date 14 Feb 2024
Estimate Approval 11 Feb 2024
NIT Approval 01 Mar 2024
Tender Closing 07 Mar 2024
Price bid opening 11 Mar 2024

Approval Dates

Workorder Date 02 May 2024
NA 06 May 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kannur WS Sn AE 2
Date: 27/12/2025

Work in progress | 50% Completed

Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid.

Kannur WS Sn AE 2
Date: 23/12/2025

Work in progress | 50% Completed

Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid.