Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit work of Sports council of Kerala- Replacing the existing the damaged service line of Kerala state sports council inside the compound of Central stadium Thiruvananthapuram

Project Deposit work of Sports council of Kerala- Replacing the existing the damaged service line of Kerala state sports council inside the compound of Central stadium Thiruvananthapuram
Project Code TVMGOK102212709
Type Main project
Funding Agency GOK
Category Deposit Work
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Replacing the existing the damaged service line of Kerala state sports council inside the compound of Central stadium Thiruvananthapuram
Status Completed
District Thiruvananthapuram
Executing Office Kuriathy Sewerage Sn 2
AS Amount (Rs) 507000
AS Number KSSC/D1-2270/22
TS Amount (Rs) 507000
TS Number 3733/2022-23
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 50
Capacity in MLD 0.00
Actual Project Completion Date 31 Mar 2023
Coverage Central stadium
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work of Sports council of Kerala- Replacing the existing the damaged service line of Kerala state sports council inside the compound of Central stadium Thiruvananthapuram Kuriathy Sewerage Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Apr 2023 Work completed on 31.03.2023 Kuriathy Sewerage Sn2 AE
31 Mar 2023 Work completed Kuriathy Sewerage Sn2 AE
20 Mar 2023 Restoration to be done. Scheduled to be done on 27.03.2023 Kuriathy Sewerage Sn2 AE
16 Mar 2023 Pipe laying completed and the manholes which covered during the inter lock work arranged by the sports council raised. Restoration in the will be carry out after compaction Kuriathy Sewerage Sn2 AE
12 Mar 2023 Oral sanction from KRFB obtained for road cutting. Trench work for laying the remaining 13 m pipe in progress Kuriathy Sewerage Sn2 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/11/2022
Scheduled date of Completion of the Project 15 Nov 2022
Expected date of Completion 31/03/2023

Processing Dates

AS Date 11 Oct 2022
TS Date 22 Oct 2022

Other details

Project Officers View