- Home
- Deposit work of Sports council of Kerala...
Deposit work of Sports council of Kerala- Replacing the existing the damaged service line of Kerala state sports council inside the compound of Central stadium Thiruvananthapuram
Project |
Deposit work of Sports council of Kerala- Replacing the existing the damaged service line of Kerala state sports council inside the compound of Central stadium Thiruvananthapuram |
Project Code |
TVMGOK102212709 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Replacing the existing the damaged service line of Kerala state
sports council inside the compound of Central stadium Thiruvananthapuram |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kuriathy Sewerage Sn 2 |
AS Amount (Rs) |
507000
|
AS Number |
KSSC/D1-2270/22 |
TS Amount (Rs) |
507000 |
TS Number |
3733/2022-23 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
50 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
31 Mar 2023 |
Coverage |
Central stadium |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Sports council of Kerala- Replacing the existing the damaged service line of Kerala state sports council inside the compound of Central stadium Thiruvananthapuram |
Kuriathy Sewerage Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Apr 2023 |
Work completed on 31.03.2023 |
Kuriathy Sewerage Sn2 AE |
|
31 Mar 2023 |
Work completed |
Kuriathy Sewerage Sn2 AE |
|
20 Mar 2023 |
Restoration to be done. Scheduled to be done on 27.03.2023 |
Kuriathy Sewerage Sn2 AE |
|
16 Mar 2023 |
Pipe laying completed and the manholes which covered during the inter lock work arranged by the sports council raised. Restoration in the will be carry out after compaction
|
Kuriathy Sewerage Sn2 AE |
|
12 Mar 2023 |
Oral sanction from KRFB obtained for road cutting. Trench work for laying the remaining 13 m pipe in progress |
Kuriathy Sewerage Sn2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/11/2022 |
Scheduled date of Completion of the Project |
15 Nov 2022 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
11 Oct 2022 |
TS Date |
22 Oct 2022 |