Deposit work 2019-2020- Madappally block panchayath - Extension of pipe line and providing street tap in Kaithamattom Nalpathamkulam Chethipuzha road at Madappally Grama panchayath

Project Deposit work 2019-2020- Madappally block panchayath - Extension of pipe line and providing street tap in Kaithamattom Nalpathamkulam Chethipuzha road at Madappally Grama panchayath
Project Code KTMDEPO08207511
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Madappally block panchayath - Extension of pipe line and providing street tap in Kaithamattom Nalpathamkulam Chethipuzha road at Madappally Grama panchayath
Status Completed
District Kottayam
Executing Office Changanassery Sn
AS Amount (Rs) 818000
AS Number B-715/19
TS Amount (Rs) 818000
TS Number TS/2020-2021/2020/5430
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 600
Capacity in MLD 0.02
Actual Project Completion Date Date is not specified
Coverage On going
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work 2019-2020- Madappally block panchayath - Extension of pipe line and providing street tap in Kaithamattom Nalpathamkulam Chethipuzha road at Madappally Grama panchayath Changanassery Sub Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Nov 2021 Pipe line work completed and reconcreting pending Thiruvalla PH Dn EE
11 Nov 2021 65% work completed. Road cutting sanction pending. Thiruvalla PH Dn EE
19 Oct 2021 65% work completed. Road cutting sanction pending. Thiruvalla PH Dn EE
11 Oct 2021 65% work completed. Road cutting sanction pending. Thiruvalla PH Dn EE
25 Sep 2021 65% work completed. Road cutting sanction pending. Thiruvalla PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/02/2021
Scheduled date of Completion of the Project 16 May 2021
Expected date of Completion 26/07/2021

Processing Dates

AS Date 22 Aug 2020
TS Date 15 Sep 2020

Other details

Project Officers View