Deposit work 2019-2020- Madappally block panchayath - Extension of pipe line and providing street tap in Kaithamattom Nalpathamkulam Chethipuzha road at Madappally Grama panchayath
Project |
Deposit work 2019-2020- Madappally block panchayath - Extension of pipe line and providing street tap in Kaithamattom Nalpathamkulam Chethipuzha road at Madappally Grama panchayath |
Project Code |
KTMDEPO08207511 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Madappally block panchayath - Extension of pipe line and providing street tap in Kaithamattom Nalpathamkulam Chethipuzha road at Madappally Grama panchayath |
Status |
Completed |
District |
Kottayam |
Executing Office |
Changanassery Sn |
AS Amount (Rs) |
818000
|
AS Number |
B-715/19 |
TS Amount (Rs) |
818000 |
TS Number |
TS/2020-2021/2020/5430 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
600 |
Capacity in MLD |
0.02 |
Actual Project Completion Date |
Date is not specified |
Coverage |
On going |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work 2019-2020- Madappally block panchayath - Extension of pipe line and providing street tap in Kaithamattom Nalpathamkulam Chethipuzha road at Madappally Grama panchayath |
Changanassery Sub Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Nov 2021 |
Pipe line work completed and reconcreting pending |
Thiruvalla PH Dn EE |
|
11 Nov 2021 |
65% work completed. Road cutting sanction pending. |
Thiruvalla PH Dn EE |
|
19 Oct 2021 |
65% work completed. Road cutting sanction pending. |
Thiruvalla PH Dn EE |
|
11 Oct 2021 |
65% work completed. Road cutting sanction pending. |
Thiruvalla PH Dn EE |
|
25 Sep 2021 |
65% work completed. Road cutting sanction pending. |
Thiruvalla PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/02/2021 |
Scheduled date of Completion of the Project |
16 May 2021 |
Expected date of Completion |
26/07/2021 |
Processing Dates
AS Date |
22 Aug 2020 |
TS Date |
15 Sep 2020 |