Project | State plan 18-19 :RDWSS - Rennovation of WTP compound at Karalam |
---|---|
Project Code | TCRGOK08185954 |
Type | Main project |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Rennovation of WTP compound at Karalam |
Status | Completed |
District | Thrissur |
Executing Office | Irinjalakkuda PH Sub Dn |
AS Amount (Rs) | 400000 |
AS Number | G.O.(Rt) No.615/2018/WRD |
TS Amount (Rs) | 400000 |
TS Number | TS/2018-2019/2018/11728 |
Total Bill Submitted (Rs) | 237785 |
Total Bill Paid (Rs) | 237785 |
Population Benefitted | 100000 |
Capacity in MLD | 5.60 |
Actual Project Completion Date | 20 Nov 2019 |
Coverage | Covers Karalam, Padiyur and Poomangalam |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Jun 2021 | Work completed on 20-11-2019 and FCC paid | Irinjalakkuda PH Dn EE | |
16 Feb 2021 | FCC paid. | Irinjalakkuda PH Dn EE | |
27 Jan 2021 | Bill submitted to Head Office. | Irinjalakkuda PH Dn EE | |
25 Jan 2021 | Work completed and bill submitted to division on 6.2.2020 | Irinjalakkuda PH Dn EE |
Date of start of Project | 28/10/2019 |
---|---|
Scheduled date of Completion of the Project | 23 Apr 2019 |
Expected date of Completion | 20/11/2019 |
AS Date | 20 Aug 2018 |
---|---|
TS Date | 11 Oct 2018 |
Project Officers | View |
---|