- Home
- DRW 2022 -2023 - CARWSS to Thiruvilwamal...
DRW 2022 -2023 - CARWSS to Thiruvilwamala & Kondazhy Villages -Various Electrical Maintenance of WTP Kuthampully
Project |
DRW 2022 -2023 - CARWSS to Thiruvilwamala & Kondazhy Villages -Various Electrical Maintenance of WTP Kuthampully |
Project Code |
TCRGOK092214315 |
Type |
Main project |
Funding Agency |
GOK |
Category |
DRW |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
DRW 2022 -2023 - CARWSS to Thiruvilwamala & Kondazhy Villages -Various Electrical Maintenance of WTP Kuthampully |
Status |
Completed |
District |
Thrissur |
Executing Office |
Chelakkara Sn |
AS Amount (Rs) |
300000
|
AS Number |
22605/AEII(OP)/2022/KWA(I) |
TS Amount (Rs) |
289000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/6071/2023_6_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
4000 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
14 Jul 2023 |
Coverage |
Thiruvilwamala GP |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DRW 2022 -2023 - CARWSS to Thiruvilwamala & Kondazhy Villages -Various Electrical Maintenance of WTP KuthampullyDRW 2022 -2023 - CARWSS to Thiruvilwamala & Kondazhy Villages -Various Electrical Maintenance of WTP Kuthampully |
Chelakkara Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Jul 2023 |
Work completed by 14/07/23 |
Chelakkara AE |
|
29 Jul 2023 |
Work completed by 14/07/23 |
Chelakkara AE |
|
27 Jul 2023 |
Electrical work going on at Kuthampully WTP |
Chelakkara AE |
|
24 Jul 2023 |
Electrical work going on at Kuthampully WTP |
Chelakkara AE |
|
19 Jul 2023 |
Electrical work going on at Kuthampully WTP |
Chelakkara AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/04/2023 |
Scheduled date of Completion of the Project |
02 May 2023 |
Expected date of Completion |
31/08/2023 |
Processing Dates
AS Date |
01 Sep 2022 |
TS Date |
29 Mar 2023 |