JJM 2021-22 and State plan - Construction of 22mld WTP, 21LL OHSR, 5LL GLSR, 12 LL OHSR, Clear water pumping mains etc for Cherpullassery, Ananganady, Chalavara and Thrikkadeeri
Project |
JJM 2021-22 and State plan - Construction of 22mld WTP, 21LL OHSR, 5LL GLSR, 12 LL OHSR, Clear water pumping mains etc for Cherpullassery, Ananganady, Chalavara and Thrikkadeeri |
Project Code |
PKDGOK07218181 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Plan plus central |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
The proposed project is for providing Comprehensive Water Supply Scheme to the entire population of Cherpulassery Municipality at the rate 150 lpcd for the projected population of 45413 forthe year 2050 . The scheme CWSS to Cherpulassery and Adj. Panchayaths is a comprehensive water supply scheme to Cherpulassery Municipality, Anangandi, Thrikkediri and Chalavara Panchayaths. The project is proposed to be executed in 3 phases. Phase – I shall comprise of the common components along with the OHSRs, GLSRs, Clear Water pumps, Clear Water Pumping / Gravity mains, distribution network of the three panchayaths. Phase – II & III shall comprise of the components required for providing water supply to Cherpulassery Municipality and providing FHTCs. |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
1878100000
|
AS Number |
G.O.(Rt)No.401/2022/WRD Dated,Thiruvananthapuram |
TS Amount (Rs) |
661000000 |
TS Number |
TS/2022-2023/2022/19808 |
Total Bill Submitted (Rs) |
82765053 |
Total Bill Paid (Rs) |
82765053 |
Population Benefitted |
45413 |
Capacity in MLD |
22.00 |
Actual Project Completion Date |
31 Dec 2024 |
Coverage |
Cherpullassery Muncipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM- CWSS to Cherpulassery Municiaplity and Adj. Panchayaths – Augmentation of Cherpulassery Urban Zone Phase II |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 May 2024 |
INTAKE WELL :-Retaining wall final lift shuttering & Retaining wall earth filling on going and final lift shuttering work started. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- PCC on Clariflocculator bottom reinforcement work. Approch road work in progress. Plastering 75% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- Beam reinforcement work. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. |
Palakkad Proj Dn AE 4 |
|
06 May 2024 |
INTAKE WELL :-Retaining wall RCC work completed & concrete work finished at intake well. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- PCC on Clariflocculator excavated land central shaft wall concreting and thrust bearing concreting. Approch road work in progress. Plastering 73% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- Beam reinforcement work. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. |
Palakkad Proj Dn AE 4 |
|
04 May 2024 |
INTAKE WELL :-Retaining wall RCC work started & concrete work finished at intake well. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- Clariflocculator central shaft wall concreting and thrust bearing concreting. Approch road work in progress. Plastering 72% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- beam bottom shuttering work. Column beam concrete work completed. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. |
Palakkad Proj Dn AE 4 |
|
02 May 2024 |
INTAKE WELL :-Retaining wall RCC work started & concrete work finished at intake well. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- Clariflocculator central shaft wall concreting and thrust bearing concreting. Approch road work in progress. Plastering 72% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- beam bottom shuttering work. Column beam concrete work completed. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. |
Palakkad Proj Dn AE 4 |
|
30 Apr 2024 |
NTAKE WELL :-Retaining wall concrete work at intake well. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- Approch road work in progress. Plastering 70% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- beam bottom shuttering work. Column beam concrete work completed. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. |
Palakkad Proj Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/10/2022 |
Scheduled date of Completion of the Project |
12 Apr 2024 |
Expected date of Completion |
12/10/2024 |
Processing Dates
AS Date |
13 May 2022 |
TS Date |
21 Jun 2022 |