JJM 2021-22 and State plan - Construction of 22mld WTP, 21LL OHSR, 5LL GLSR, 12 LL OHSR, Clear water pumping mains etc for Cherpullassery, Ananganady, Chalavara and Thrikkadeeri

Project JJM 2021-22 and State plan - Construction of 22mld WTP, 21LL OHSR, 5LL GLSR, 12 LL OHSR, Clear water pumping mains etc for Cherpullassery, Ananganady, Chalavara and Thrikkadeeri
Project Code PKDGOK07218181
Type Main project
Funding Agency GOK
Category Plan plus central
Type of scheme Water Supply
Scheme 2215-02-106-97
Description The proposed project is for providing Comprehensive Water Supply Scheme to the entire population of Cherpulassery Municipality at the rate 150 lpcd for the projected population of 45413 forthe year 2050 . The scheme CWSS to Cherpulassery and Adj. Panchayaths is a comprehensive water supply scheme to Cherpulassery Municipality, Anangandi, Thrikkediri and Chalavara Panchayaths. The project is proposed to be executed in 3 phases. Phase – I shall comprise of the common components along with the OHSRs, GLSRs, Clear Water pumps, Clear Water Pumping / Gravity mains, distribution network of the three panchayaths. Phase – II & III shall comprise of the components required for providing water supply to Cherpulassery Municipality and providing FHTCs.
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 1878100000
AS Number G.O.(Rt)No.401/2022/WRD Dated,Thiruvananthapuram
TS Amount (Rs) 661000000
TS Number TS/2022-2023/2022/19808
Total Bill Submitted (Rs) 82765053
Total Bill Paid (Rs) 82765053
Population Benefitted 45413
Capacity in MLD 22.00
Actual Project Completion Date 31 Dec 2024
Coverage Cherpullassery Muncipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM- CWSS to Cherpulassery Municiaplity and Adj. Panchayaths – Augmentation of Cherpulassery Urban Zone Phase II Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 INTAKE WELL :-Retaining wall final lift shuttering & Retaining wall earth filling on going and final lift shuttering work started. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- PCC on Clariflocculator bottom reinforcement work. Approch road work in progress. Plastering 75% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- Beam reinforcement work. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. Palakkad Proj Dn AE 4
06 May 2024 INTAKE WELL :-Retaining wall RCC work completed & concrete work finished at intake well. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- PCC on Clariflocculator excavated land central shaft wall concreting and thrust bearing concreting. Approch road work in progress. Plastering 73% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- Beam reinforcement work. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. Palakkad Proj Dn AE 4
04 May 2024 INTAKE WELL :-Retaining wall RCC work started & concrete work finished at intake well. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- Clariflocculator central shaft wall concreting and thrust bearing concreting. Approch road work in progress. Plastering 72% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- beam bottom shuttering work. Column beam concrete work completed. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. Palakkad Proj Dn AE 4
02 May 2024 INTAKE WELL :-Retaining wall RCC work started & concrete work finished at intake well. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- Clariflocculator central shaft wall concreting and thrust bearing concreting. Approch road work in progress. Plastering 72% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- beam bottom shuttering work. Column beam concrete work completed. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. Palakkad Proj Dn AE 4
30 Apr 2024 NTAKE WELL :-Retaining wall concrete work at intake well. Substation column up to floor level completed. 21 LL OHSR Thrikkaderi :- Hand rails throughout the tank are completed , plastering is ongoing .22 MLD WTP Cherpulassery :- Approch road work in progress. Plastering 70% completed, handrail work completed. Filter gallery; plastering on going. Operating platform completed. 12 LL OHSR Chalavara:- beam bottom shuttering work. Column beam concrete work completed. Bottom column work completed. 5 LL OHSR Ananganadi :- not started. Palakkad Proj Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 13/10/2022
Scheduled date of Completion of the Project 12 Apr 2024
Expected date of Completion 12/10/2024

Processing Dates

AS Date 13 May 2022
TS Date 21 Jun 2022

Other details