| Project | Jal Jeevan Mission (JJM)-Balance work of laying and providing FHTcs in Dharmadam panchayath-Jal jeevan mission-Kannur district-Dharmadam panchayath phase II -WSS to Thalassery Mahe and adjoining panchayath laying distribution system and providing FHTcs –balance 736 nos |
|---|---|
| Project Code | KNRJJM08202932P3 |
| Type | Package |
| Main Project | JJM-Kannur District- Dharmadam Panchayath-WSS to Thalassery, Mahe and adjoining Panchayaths - Phase II |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission (JJM)-Balance work of laying and providing FHTcs in Dharmadam panchayath-Jal jeevan mission-Kannur district-Dharmadam panchayath phase II -WSS to Thalassery Mahe and adjoining panchayath laying distribution system and providing FHTcs –balance 736 nos |
| Status | On-going |
| District | Kannur |
| Executing Office | Thalassery PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 22100000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/6993/2022_26_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | 28 Apr 2023 |
| Expected date of Completion | 28/04/2023 |
| TS Date | 07 Jan 2023 |
|---|
| Workorder Date | 07 Feb 2023 |
|---|---|
| NA | 28 Feb 2023 |
| Thalassery PH Sn AE |
| Date: 22/12/2023 |
Work has been completed | 100% Completed
Work completed & final bill under preparation.
| Thalassery PH Sn AE |
| Date: 15/12/2023 |
Work has been completed | 100% Completed
Work completed & final bill under preparation .