Project | MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation |
---|---|
Project Code | EKMGOK08218581P1 |
Type | Package |
Main Project | MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation |
Funding Agency | GOK |
Category | MLA SDF |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation |
Status | On-going |
District | Ernakulam |
Executing Office | Karuvelippady WW Sn 1 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 164000 |
TS Number | TS/2021-2022/6561 |
Technical specification | MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation |
Contractor | sHONEY p jOSEPH (Mob: 9745608387) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 25/10/2021 |
---|---|
Scheduled date of Completion as per agreement | 24 Nov 2021 |
Expected date of Completion | 31/03/2022 |
TS Date | 24 Aug 2021 |
---|---|
Estimate Approval | 30 Aug 2021 |
NIT Approval | 01 Sep 2021 |
Tender Closing | 06 Sep 2021 |
Technichal Pre-Qualification | 07 Sep 2021 |
Price bid opening | 08 Sep 2021 |
Workorder Date | 11 Oct 2021 |
---|---|
NA | 25 Oct 2021 |
Karuvelippady AEE |
Date: 16/09/2022 |
Work has been completed | 100% Completed
Bill submitted to Division office .
Karuvelippady AEE |
Date: 15/09/2022 |
Work has been completed | 100% Completed
Bill submitted to Division office .