Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation

Project MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation
Project Code EKMGOK08218581P1
Type Package
Main Project MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation
Funding Agency GOK
Category MLA SDF
Type of scheme Water Supply
Scheme 2215-02-106-97
Description MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation
Status On-going
District Ernakulam
Executing Office Karuvelippady WW Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 164000
TS Number TS/2021-2022/6561
Technical specification MLA SDF - Supplying and laying 63mm PVC pipe in place of damaged 50mm GI pipe at Kurisingal lane in Division No 14(old) in Kochi corporation
Contractor sHONEY p jOSEPH (Mob: 9745608387)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/10/2021
Scheduled date of Completion as per agreement 24 Nov 2021
Expected date of Completion 31/03/2022

Processing Dates

TS Date 24 Aug 2021
Estimate Approval 30 Aug 2021
NIT Approval 01 Sep 2021
Tender Closing 06 Sep 2021
Technichal Pre-Qualification 07 Sep 2021
Price bid opening 08 Sep 2021

Approval Dates

Workorder Date 11 Oct 2021
NA 25 Oct 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Karuvelippady AEE
Date: 16/09/2022

Work has been completed | 100% Completed

Bill submitted to Division office .

Karuvelippady AEE
Date: 15/09/2022

Work has been completed | 100% Completed

Bill submitted to Division office .