Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

WSS to Vilappil panchayath-Construction of Intake Well,Supplying and Laying Raw water Pumping main,Construction of WTP and allied works ,Construction of OHSR

Project WSS to Vilappil panchayath-Construction of Intake Well,Supplying and Laying Raw water Pumping main,Construction of WTP and allied works ,Construction of OHSR
Project Code TVMGOK0317494
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description WSS to Vilappil panchayath-Construction of Intake Well, Supplying and Laying Raw water Pumping main, Construction of WTP and allied works , Construction of OHSR
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 160000000
AS Number GO(Rt)No.330/2016/WRD
TS Amount (Rs) 151893000
TS Number KWA/CE(SR)/8/2016-17
Total Bill Submitted (Rs) 43489247
Total Bill Paid (Rs) 26578530
Population Benefitted 120912
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage Benefited population 120912
Work Plan Download

Packages

No. Project Name Location View
1 Clear Water Pumping main from WTP to Kavinpuram Trivandrum Project Dn
2 Clear Water Transmission main from WTP to Peyad and CWPM to nooliyode Trivandrum Project Dn
3 Supply and Installation of Raw Water and Clear water pumps Trivandrum Project Dn
4 Supply and installation of Transformers. Trivandrum Project Dn
5 Water Supply to Vilappil Panchayath - Design and Construction of Weir across Karamana River at Kavadikadavu Trivandrum Project Dn
6 WSS to Vilappil panchayath-Construction of Intake Well,Supplying and Laying Raw water Pumping main,Construction of WTP and allied works ,Construction of OHSR Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Jul 2022 Mechanical work completed, Compound wall construction completed. Laterals at the filter bed laid. Filter medii to be laid.Pumps are supplied and the installation is going on.Earthing and allied works are going on in connection with the installation of Transformer.Transmission main from OHSR to Peyad and from Kavinpuram to Nooliyodu is completed.The Panchayath authorities already agreed to construct the wash water drain from the plant in the presence of MLA 's meeting.But still the work is not done. Thiruvananthapuram Project AE1
06 Jul 2022 Mechanical work completed, Compound wall construction completed. Laterals at the filter bed laid. Filter medii to be laid.Pumps are supplied and the installation is going on.Earthing and allied works are going on in connection with the installation of Transformer.Transmission main from OHSR to Peyad and from Kavinpuram to Nooliyodu is completed.The Panchayath authorities already agreed to construct the wash water drain from the plant in the presence of MLA 's meeting.But still the work is not done. Thiruvananthapuram Project AE1
05 Jul 2022 Mechanical work completed, Compound wall construction completed. Laterals at the filter bed laid. Filter medii to be laid.Pumps are supplied and the installation is going on.Earthing and allied works are going on in connection with the installation of Transformer.Transmission main from OHSR to Peyad and from Kavinpuram to Nooliyodu is completed. Thiruvananthapuram Project AE1
14 Mar 2022 Inside plastering work is progressing and hand rail at OHSR and at the step of stair case continuing.and costruction of Aerator completed .Painting work is progressing. Thiruvananthapuram Project AE1
07 Feb 2022 Inside plastering work is progressing and hand rail at OHSR and at the step of stair case continuing.and costruction of Aerator completed .Painting work is progressing. Thiruvananthapuram Project AE1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/03/2019
Scheduled date of Completion of the Project 12 Dec 2019
Expected date of Completion 31/08/2022

Processing Dates

AS Date 31 Mar 2016
TS Date 07 Jul 2016

Other details

Project Officers View