Jal Jeevan Mission (JJM)-JJM Connections in Manakody Pullu Road-JJM Connections in Manakody Pullu Road, Indira nagar, Schools, Govt Institutions etc complete-Pipeline Work

Project Jal Jeevan Mission (JJM)-JJM Connections in Manakody Pullu Road-JJM Connections in Manakody Pullu Road, Indira nagar, Schools, Govt Institutions etc complete-Pipeline Work
Project Code TCRJJM082012424
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM Connections in Manakody Pullu Road, Indira nagar, Schools, Govt Institutions etc complete-Pipeline Work
Status Completed
District Thrissur
Executing Office Thrissur WW Sn 2
AS Amount (Rs) 25000000
AS Number 541/2020/WRD
TS Amount (Rs) 890000
TS Number WRD/KWA-CE(CR)/EST-TS/5109/2022-26-1-1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 500
Capacity in MLD 0.50
Actual Project Completion Date Date is not specified
Coverage Manakody Pullu area in Manalur Pt
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM Connections in Manakody Pullu Road-JJM Connections in Manakody Pullu Road, Indira nagar, Schools, Govt Institutions etc complete-Pipeline Work Thrissur WW Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Feb 2024 Bill under preparation Thrissur WW Sn - AE 2
08 Feb 2024 Bill under preparation Thrissur WW Sn - AE 2
23 Jun 2023 Completed and bill under preparation. By mistake 5 connections of 5th SLSSC -Arimpur is added to this work. Actually 26 connections are provided in this work. Thrissur PH Dn EE
07 Jun 2023 Completed and bill under preparation. 31 connections given. Thrissur PH Dn EE
05 Jun 2023 Completed and bill under preparation. 31 connections given. Thrissur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/09/2022
Scheduled date of Completion of the Project 26 Oct 2022
Expected date of Completion 31/05/2023

Processing Dates

AS Date 21 Aug 2019
TS Date 16 Sep 2022

Other details