CWSS to Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery & Panchayaths Phase I
Project |
CWSS to Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery & Panchayaths Phase I |
Project Code |
PTAGOK0317605 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Comprehensive water supply scheme to Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery panchayaths in Pathanamthitta district- Production components. |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Adoor Project Dn |
AS Amount (Rs) |
423500000
|
AS Number |
GO(Rt.)No.269/2017/WRD dt.30.3.17 |
TS Amount (Rs) |
|
TS Number |
not issued |
Total Bill Submitted (Rs) |
9007000 |
Total Bill Paid (Rs) |
9007000 |
Population Benefitted |
163525 |
Capacity in MLD |
36.00 |
Actual Project Completion Date |
31 Jul 2023 |
Coverage |
Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery panchayaths |
Packages
No. |
Project Name |
Location |
View |
1 |
CWSS to Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery & Panchayaths Phase I |
Adoor Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Nov 2022 |
Rs. 10.59 crores to be remitted to Dy Collector, Pathanamthitta for land acquisition. Fund request submitted to FM but not allotted. Last date for remitting to DY Collector LA is 5/12/2022. If funds not remitted by that date, the project itself will be jeopardized. |
Adoor Project Dn EE |
|
30 Aug 2022 |
Not started. Land valuation completed. Fund request submitted |
Adoor Project Dn AE3 |
|
18 Jul 2022 |
Not started. Land valuation completed. Fund request submitted |
Adoor Project Dn AE3 |
|
10 Jul 2022 |
Not started. Land valuation completed. Fund request submitted |
Adoor Project Dn AE3 |
|
30 Jun 2022 |
Land acquisition stopped due to court case |
Adoor Project Dn AE3 |
|
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
06 Jul 2022 |
Pending |
Pending |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
Rs. 10.59 crores to be remitted to Dy Collector, Pathanamthitta for land acquisition. Fund request submitted to FM but not allotted. Last date for remitting to DY Collector LA is 5/12/2022. |
No comments available. |
Pending |
Duration & Sanction dates
Date of start of Project |
01/11/2018 |
Scheduled date of Completion of the Project |
30 Jun 2023 |
Expected date of Completion |
31/12/2023 |