CWSS to Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery & Panchayaths Phase I

Project CWSS to Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery & Panchayaths Phase I
Project Code PTAGOK0317605
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Comprehensive water supply scheme to Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery panchayaths in Pathanamthitta district- Production components.
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
AS Amount (Rs) 423500000
AS Number GO(Rt.)No.269/2017/WRD dt.30.3.17
TS Amount (Rs)
TS Number not issued
Total Bill Submitted (Rs) 9007000
Total Bill Paid (Rs) 9007000
Population Benefitted 163525
Capacity in MLD 36.00
Actual Project Completion Date 31 Jul 2023
Coverage Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery panchayaths

Packages

No. Project Name Location View
1 CWSS to Puramattom, Kalloopara, Ezhumattoor, Kunnamthanam, Eraviperoor, Koipuram,Thottapuzhassery & Panchayaths Phase I Adoor Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Nov 2022 Rs. 10.59 crores to be remitted to Dy Collector, Pathanamthitta for land acquisition. Fund request submitted to FM but not allotted. Last date for remitting to DY Collector LA is 5/12/2022. If funds not remitted by that date, the project itself will be jeopardized. Adoor Project Dn EE
30 Aug 2022 Not started. Land valuation completed. Fund request submitted Adoor Project Dn AE3
18 Jul 2022 Not started. Land valuation completed. Fund request submitted Adoor Project Dn AE3
10 Jul 2022 Not started. Land valuation completed. Fund request submitted Adoor Project Dn AE3
30 Jun 2022 Land acquisition stopped due to court case Adoor Project Dn AE3

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
06 Jul 2022 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) Rs. 10.59 crores to be remitted to Dy Collector, Pathanamthitta for land acquisition. Fund request submitted to FM but not allotted. Last date for remitting to DY Collector LA is 5/12/2022. No comments available. Pending

Duration & Sanction dates

Date of start of Project 01/11/2018
Scheduled date of Completion of the Project 30 Jun 2023
Expected date of Completion 31/12/2023

Processing Dates

AS Date 30 Mar 2017

Other details

Project Officers View