| Project | PACKAGE VIII- CONSTRUCTION OF 5.25 LL CAPACITY OHSR AT PATTATHIKKUNNU , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN NEW MAHE GRAMA PANCHAYATH |
|---|---|
| Project Code | KNRJJM022213306P8 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of 5.25 LL capacity OHSR at Pattathikkunnu, demolishing the old OHSR , supplying ,laying and commissioning distribution system and providing FHTCs |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 322300000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/10644/2022_26_1_1 |
| Technical specification | Construction of 5.25 LL capacity OHSR at Pattathikkunnu, demolishing the old OHSR , supplying ,laying and commissioning distribution system and providing FHTCs |
| Contractor | STREFA PROJECTS PRIVATE LIMITED & KSAHMIRILAL CONSTRUCTIONS (P) LTD-JV (Mob: 9160012315) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 07/06/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 06 Jun 2024 |
| Expected date of Completion | 31/12/2025 |
| TS Date | 17 Nov 2022 |
|---|---|
| Estimate Approval | 17 Nov 2022 |
| NIT Approval | 17 Dec 2022 |
| Tender Closing | 27 Apr 2024 |
| Technichal Pre-Qualification | 27 Nov 2023 |
| Price bid opening | 29 Apr 2024 |
| Workorder Date | 08 May 2023 |
|---|---|
| NA | 05 Jun 2023 |
| Mattannur Project Sn 2 AE |
| Date: 05/01/2026 |
Work in progress | 60% Completed
Total distribution is 92.986 km.Pipe required is 87.982 km. in that 81.218 km Pipe has supplied. Pipe laying of 68.7 km completed. House connection and HTC work is on going, 1816 nos. HTC completed.Total meter fixed is 2085 no. construction of Temporary MS Tank completed and commissioned. Demolishing the old OHSR 100% completed . Railway line crossing by HDD method at peringadi railway crossing (28.5m) completed. At Punnol(16.5m (PWD-NH) push through completed. Kidarankunnu(PWD-NH) started. Partial charging, line supply & interconnection at kidarankunnu completed.240nos HTC completed in to FHTC. Punnol in progress, LSGD Road restoration in progress, 14 km completed. PWD restoration 1.9km tarring comleted..
| Mattannur Project Sn 2 AE |
| Date: 30/12/2025 |
Work in progress | 60% Completed
Total distribution is 92.986 km in that 81.218 km Pipe has supplied. Pipe laying of 68.7 km completed. House connection and HTC work is on going, 1816 nos. HTC completed.Total meter fixed is 2085 no. construction of Temporary MS Tank completed and commissioned. Demolishing the old OHSR 100% completed . Railway line crossing by HDD method at peringadi railway crossing (28.5m) completed. At Punnol(16.5m (PWD-NH) push through completed. Kidarankunnu(PWD-NH) started. Partial charging, line supply & interconnection at kidarankunnu completed.240nos HTC completed in to FHTC. Punnol in progress, LSGD Road restoration in progress, 14 km completed. PWD restoration 1.9km tarring comleted..