Project | PACKAGE VIII- CONSTRUCTION OF 5.25 LL CAPACITY OHSR AT PATTATHIKKUNNU , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN NEW MAHE GRAMA PANCHAYATH |
---|---|
Project Code | KNRJJM022213306P8 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Construction of 5.25 LL capacity OHSR at Pattathikkunnu, demolishing the old OHSR , supplying ,laying and commissioning distribution system and providing FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 322300000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/10644/2022_26_1_1 |
Technical specification | Construction of 5.25 LL capacity OHSR at Pattathikkunnu, demolishing the old OHSR , supplying ,laying and commissioning distribution system and providing FHTCs |
Contractor | STREFA PROJECTS PRIVATE LIMITED & KSAHMIRILAL CONSTRUCTIONS (P) LTD-JV (Mob: 9160012315) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 07/06/2023 |
---|---|
Scheduled date of Completion as per agreement | 06 Jun 2024 |
Expected date of Completion | 31/12/2025 |
TS Date | 17 Nov 2022 |
---|---|
Estimate Approval | 17 Nov 2022 |
NIT Approval | 17 Dec 2022 |
Tender Closing | 27 Apr 2024 |
Technichal Pre-Qualification | 27 Nov 2023 |
Price bid opening | 29 Apr 2024 |
Workorder Date | 08 May 2023 |
---|---|
NA | 05 Jun 2023 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 54% Completed
EARTH EXCAVATION AND PIPE LAYING IS IN PROGRESS. Total distribution is 93 km in that 76.224 km Pipe has supplied. Pipe laying of 66.53 km completed. House connection and HTC work is on going,1609 nos. HTC completed. construction of Temporary MS Tank completed and commissioned. Demolishing the old OHSR 100% demolishing completed . DI Pipe laying of 200 mm& 90mm 8kg PVC distribution, Transmission is in progress at salafi masjid road, Railway line crossing by HDD method at peringadi railway crossing completed. LSGD Road restoration in progress, 6 km completed.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 53% Completed
EARTH EXCAVATION AND PIPE LAYING IS IN PROGRESS. Total distribution is 93 km in that 76.224 km Pipe has supplied. Pipe laying of 66.072 km completed. House connection and HTC work is on going,1609 nos. HTC completed. construction of Temporary MS Tank completed and commissioned. Demolishing the old OHSR 100% demolishing completed . DI Pipe laying of 200 mm& 90mm 8kg PVC distribution, Transmission is in progress at salafi masjid road, Railway line crossing by HDD method at peringadi started. LSGD Road restoration in progress.6 km completed.