Deposit work of Kasaragod Municipality- Pipe line extension to K K Puram

Project Deposit work of Kasaragod Municipality- Pipe line extension to K K Puram
Project Code KGDDEPO03218274
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Pipe line extension to K K Puram
Status Completed
District Kasaragod
Executing Office Kasargod PH Dn
AS Amount (Rs) 2500000
AS Number P2-12932/2020
TS Amount (Rs) 2500000
TS Number TS/2021-2022/2019/22515
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 13 Apr 2022
Coverage

Packages

No. Project Name Location View
1 Deposit work of Kasaragod Municipality- Pipe line extension to K K Puram Kasargod WSP Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 work completed on 13/04/2022 Kasargod WSP Sn AE
09 May 2024 work completed on 13/04/2022 Kasargod WSP Sn AE
07 May 2024 work completed on 13/04/2022 Kasargod WSP Sn AE
30 Apr 2024 work completed on 13/04/2022 Kasargod WSP Sn AE
22 Apr 2024 work completed on 13/04/2022 Kasargod WSP Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 24 Feb 2022
Expected date of Completion 11/04/2022

Processing Dates

AS Date 01 Mar 2021
TS Date 18 Apr 2021

Other details

Project Officers View