22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-Sewage treatment plant Kureeppuzha(8569)

Project 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-Sewage treatment plant Kureeppuzha(8569)
Project Code KLMGOI0918482
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT- 2015-17-Design, Supply,Construction,Erection,Testing and Commissioning of 12 MLD capacity Sewage Treatment Plant (STP) based on Moving Bed Bio Reactor( MBBR) Technology with provision for septage handling for co-treatment with sewage and Recycling System for the treated Water including Operation & Maintenance for 10 years at Kureepuzha in Kollam corporation
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 319100000
AS Number G.O.(Rt)No.LSGD 516/2018/LSGD
TS Amount (Rs) 298690000
TS Number TS/2018-19/2018/9433
Total Bill Submitted (Rs) 147261337
Total Bill Paid (Rs) 147261337
Population Benefitted 78022
Capacity in MLD 12.00
Actual Project Completion Date 31 Jul 2023
Coverage Division No. Name of division Population as on 2011 12 Thevally 7876 13 Vadakkumbhagham 6217 14 Ashramam 4820 17 Kadappakada 7817 44 Contonment 6680 46 Thamarakulam 5438 47 Pallithottam 6386 48 Port 7600 49 Kachery 6911 51 Thangassery 8258 Total coverage : 68003, 78022 as per 2041 population
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Sewage treatment plant Kureeppuzha(8569) Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site... Admin building column form work and staircase reinforcement work in progress...Sec.Clarifier 2- handrail work in progress...Admin building column Curing work in progress... Kollam Project HD
13 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building staircase form work in progress....Sec.Clarifier 1 handrail work in progress... Kollam Project HD
11 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Centrifuge building handrail work in progress..Admin building column form work in progress... Kollam Project HD
10 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building second lift column rcc work in progress ...Centrifuge building handrail work in progress...Drainage slab ready for concrete.... Kollam Project HD
09 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building second lift 9 column form work completed..Ready for concrete..Admin building floor levelling and staircase form work in progress..... Kollam Project HD

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/11/2020
Scheduled date of Completion of the Project 31 May 2022
Expected date of Completion 31/07/2023

Processing Dates

AS Date 22 Feb 2018
TS Date 13 Sep 2018

Other details

Project Officers View