Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit work : KRFB Improvemets to Ayur Anchal Punalur road- Laying pipe line on both sides of Ayur Anchal Punalur road

Project Deposit work : KRFB Improvemets to Ayur Anchal Punalur road- Laying pipe line on both sides of Ayur Anchal Punalur road
Project Code KLMDEPO032212068
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Utility shifting in connection with Improvements to Ayur anchal road- Laying pipe line on both sides of Ayur anchal road
Status Completed
District Kollam
Executing Office Valakom PH Sub Dn
AS Amount (Rs) 27666500
AS Number KRFB/KLM/PMU/KLM/2021
TS Amount (Rs) 25880000
TS Number 850/2022-23
Total Bill Submitted (Rs) 2297719
Total Bill Paid (Rs) 2076646
Population Benefitted 25000
Capacity in MLD 73.00
Actual Project Completion Date 04 Aug 2023
Coverage Utility shifting from Ayur to Anchal-Punalur
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work : KRFB Improvemets to Ayur Anchal road- Laying pipe line on both sides of Ayur Anchal Punalur road Valakom PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Aug 2023 Work Completed. Bill Sumitted Kottarakkara PH Dn EE
04 Aug 2023 90 mm dia 10 kg /cm2 pvc pipe 7.52 km completed. 160mm dia 10kg/cm2 pvc pipe 6.9 km completed Valakom PH Sn AE
04 Aug 2023 90 mm dia 10 kg /cm2 pvc pipe 7.52 km completed. 160mm dia 10kg/cm2 pvc pipe 6.9 km completed. Valakom PH Sn AE
01 Aug 2023 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress Valakom PH Sn AE
29 Jul 2023 12km pipe laying work on both sides is completed,existing connections are given on both sides, work in progress Valakom PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/06/2022
Scheduled date of Completion of the Project 30 Nov 2022
Expected date of Completion 30/11/2022

Processing Dates

AS Date 24 Mar 2022
TS Date 13 Apr 2022

Other details

Project Officers View