AMRUT 2.0 - Shornur Municipality Pipeline replacement/extension of various size pipes and providing 2290 FHTCs phase 1
Project |
AMRUT 2.0 - Shornur Municipality Pipeline replacement/extension of various size pipes and providing 2290 FHTCs phase 1 |
Project Code |
PKDAMRUT2112212862 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
|
Description |
AMRUT 2.0 - Shornur Municipality Pipeline replacement/extension of various size pipes and providing 2290 FHTCs phase 1 |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
121500000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
113300000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/986/2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
51085 |
Capacity in MLD |
20.00 |
Actual Project Completion Date |
24 Jan 2024 |
Coverage |
Shoranur municipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0 - Shornur Municipality Pipeline replacement/extension of various size pipes and providing 2290 FHTCs phase 1 |
Shoranur Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 May 2024 |
90mm, 110mm, 140mm, 160mm, PVC pipes laid : Total length laid = 23500m. 150mm GI Pipe laid = 600m, 125mm GI Pipe laid = 1150m, 100mm GI Pipe laid =1100 m, 80mm GI Pipe laid = 450m. FHTC's 1700nos,Retrofitting connections 610 nos. |
Shoranur PH Sn AE |
|
04 May 2024 |
90mm, 110mm, 140mm, 160mm, PVC pipes laid : Total length laid = 23500m. 150mm GI Pipe laid = 350m, 125mm GI Pipe laid = 350m, 100mm GI Pipe laid =1100 m, 80mm GI Pipe laid = 300m. FHTC's 1680nos,Retrofitting connections 610 nos. |
Shoranur PH Sn AE |
|
28 Apr 2024 |
90mm, 110mm, 140mm, 160mm, PVC pipes laid : Total length laid = 23500m. 150mm GI Pipe laid = 350m, 125mm GI Pipe laid = 350m, 100mm GI Pipe laid =1100 m, 80mm GI Pipe laid = 300m. FHTC's 1680nos,Retrofitting connections 610 nos. |
Shoranur PH Sn AE |
|
21 Apr 2024 |
90mm, 110mm, 140mm, 160mm, PVC pipes laid : Total length laid = 23500m. 150mm GI Pipe laid = 350m, 125mm GI Pipe laid = 350m, 100mm GI Pipe laid =1100 m, 80mm GI Pipe laid = 300m. FHTC's 1680nos,Retrofitting connections 610 nos. |
Shoranur PH Sn AE |
|
17 Apr 2024 |
90mm, 110mm, 140mm, 160mm, PVC pipes laid : Total length laid = 23500m. 150mm GI Pipe laid = 350m, 125mm GI Pipe laid = 350m, 100mm GI Pipe laid =1100 m, 80mm GI Pipe laid = 300m. FHTC's 1680nos,Retrofitting connections 610 nos. |
Shoranur PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/06/2023 |
Scheduled date of Completion of the Project |
18 Apr 2024 |
Expected date of Completion |
24/02/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
18 Jan 2023 |