AMRUT 2.0 -Priority 11- Improving water supply at Ponnurunni area in Kochi Corporation division no.53(new) and 31(old) by laying 160mm PVC pipe alongPonnurunni Kunjan Bava road
Project |
AMRUT 2.0 -Priority 11- Improving water supply at Ponnurunni area in Kochi Corporation division no.53(new) and 31(old) by laying 160mm PVC pipe alongPonnurunni Kunjan Bava road |
Project Code |
EKMAMRUT112214050 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT 2.0 -Priority 11- Improving water supply at Ponnurunni area in Kochi Corporation division no.53(new) and 31(old) by laying 160mm PVC pipe alongPonnurunni Kunjan Bava road |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Kochi PH Dn |
AS Amount (Rs) |
5050000
|
AS Number |
GO(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
5000000 |
TS Number |
10383/2022-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
|
Population Benefitted |
50000 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
AMRUT 2.0 -Priority 11- Improving water supply at Ponnurunni area in Kochi Corporation division no.53(new) and 31(old) by laying 160mm PVC pipe alongPonnurunni Kunjan Bava road |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0 -Priority 11- Improving water supply at Ponnurunni area in Kochi Corporation division no.53(new) and 31(old) by laying 160mm PVC pipe alongPonnurunni Kunjan Bava road |
Vytilla Section 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
Bill submitted |
Vytilla Section AE - 1 |
|
28 Oct 2023 |
Bill completed |
Vytilla Section AE - 1 |
|
20 Oct 2023 |
Bill under preparation |
Vytilla Section AE - 1 |
|
19 Oct 2023 |
Work Completed. Bill under preparation |
Kochi PH Dn EE |
|
18 Oct 2023 |
Work Completed. Bill under preparation |
Vytilla Section AE - 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/03/2023 |
Scheduled date of Completion of the Project |
15 Sep 2023 |
Expected date of Completion |
31/10/2023 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
07 Jan 2023 |