DEPOSIT WORK - PWD BRIDGES :- REPLACEMENT OF PIPE LINE FROM PIPE MUKKU TO KOOTTAMVATHUKKAL KADAVU IN CONNECTED WITH CONSTRUCTION OF KOOTTAMVATHUKKAL BRIDGE AND APPROACH ROAD IN WARD IX OF KANDALLOOR PANCHAYAT.

Project DEPOSIT WORK - PWD BRIDGES :- REPLACEMENT OF PIPE LINE FROM PIPE MUKKU TO KOOTTAMVATHUKKAL KADAVU IN CONNECTED WITH CONSTRUCTION OF KOOTTAMVATHUKKAL BRIDGE AND APPROACH ROAD IN WARD IX OF KANDALLOOR PANCHAYAT.
Project Code ALPDEPO04217444
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT WORK - PWD BRIDGES :- REPLACEMENT OF PIPE LINE FROM PIPE MUKKU TO KOOTTAMVATHUKKAL KADAVU IN CONNECTED WITH CONSTRUCTION OF KOOTTAMVATHUKKAL BRIDGE AND APPROACH ROAD IN WARD IX OF KANDALLOOR PANCHAYAT.
Status Completed
District Alappuzha
Executing Office Kayamkulam PH Sn
AS Amount (Rs) 550000
AS Number 74 of 2021-2022
TS Amount (Rs) 542300
TS Number TS/2021-2022/2021/9813
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 300
Capacity in MLD 2.00
Actual Project Completion Date 07 Jul 2021
Coverage No additional coverage
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT WORK - PWD BRIDGES :- REPLACEMENT OF PIPE LINE FROM PIPE MUKKU TO KOOTTAMVATHUKKAL KADAVU IN CONNECTED WITH CONSTRUCTION OF KOOTTAMVATHUKKAL BRIDGE AND APPROACH ROAD IN WARD IX OF KANDALLOOR PANCHAYAT. Kayamkulam PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Aug 2021 Bill submitted to sub division Kayamkulam AE
04 Aug 2021 WORK COMPLETED. AND BILL UNDER PREPARATION Kayamkulam AE
31 Jul 2021 WORK COMPLETED. AND BILL UNDER PREPARATION Kayamkulam AE
28 Jul 2021 WORK COMPLETED. AND BILL UNDER PREPARATION Kayamkulam AE
25 Jul 2021 WORK COMPLETED. AND BILL UNDER PREPARATION Kayamkulam AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 14/06/2021
Scheduled date of Completion of the Project 25 May 2021
Expected date of Completion 15/07/2021

Processing Dates

AS Date 28 Apr 2021
TS Date 04 May 2021

Other details

Project Officers View