Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

SLSSC - 2013- CARWSS to Chungathara, Pothukallu, Edakkara , and Vazhikkadavu Panchayaths in Nilambur Panchayath - Construction of 8.00 m dia Intake well cum pump house with approach bridge, Gantry girder, Retaining wall, Rest room and allied work in Chaliyar river at Pookottumannakkadavu in Chungathara Panchayath

Project SLSSC - 2013- CARWSS to Chungathara, Pothukallu, Edakkara , and Vazhikkadavu Panchayaths in Nilambur Panchayath - Construction of 8.00 m dia Intake well cum pump house with approach bridge, Gantry girder, Retaining wall, Rest room and allied work in Chaliyar river at Pookottumannakkadavu in Chungathara Panchayath
Project Code MLPGOI03146067P1
Type Package
Main Project 10-ARWSS - NRDWP-19th SLSSC 2013- CRWSS to Chungathara, Pothukallu, Edakkara and Vazhikkadavu Panchayaths in Nilambur Constituency in Malappuram District Phase 1(part-1)
Funding Agency GOI
Category NRDWP-XVSLSSC
Type of scheme Water Supply
Scheme
Description Construction of intake well, approach bridge and allied works
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Construction of 8.00 m inside dia well cum pump house at upstream side of Pookottumanna Regulator Bridge in Chungathara Panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/07/2015
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 04 Mar 2014
TS Date 17 May 2014
Estimate Approval 14 Aug 2014
Tender Closing 22 Sep 2014
Technichal Pre-Qualification 30 Oct 2014
Price bid opening 30 Oct 2014

Approval Dates

Workorder Date 26 Dec 2014
NA 15 Jan 2015

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE2
Date: 05/07/2021

Work has been completed | 100% Completed

As the work of intake well completed, and the land for other components not yet obtained, it is decided to utilize the well as the source for the new JJM assisted WSS to four Panchayaths. So, request submitted to head office to close this work. .

Malappuram Project Dn AE2
Date: 22/04/2021

Work has been completed | 100% Completed

The work Completed. For Balance works, DER is preparing under JJM.