State Plan 2024-25-Water Supply to Specified Institutions/locations-WSS to Cheruvanchery -Providing dedicated water supply to Jawahar Navodaya Vidyalaya,Chendayad-Pipeline Work

Project State Plan 2024-25-Water Supply to Specified Institutions/locations-WSS to Cheruvanchery -Providing dedicated water supply to Jawahar Navodaya Vidyalaya,Chendayad-Pipeline Work
Project Code KNRGOK072416256P1
Type Package
Main Project State Plan 2024-25-Water Supply to Specified Institutions/locations-WSS to Cheruvanchery -Providing dedicated water supply to Jawahar Navodaya Vidyalaya,Chendayad-Pipeline Work
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 4215-01-800-89
Description Water Supply to Specified Institutions/locations-WSS to Cheruvanchery -Providing dedicated water supply to Jawahar Navodaya Vidyalaya,Chendayad-Pipeline Work
Status On-going
District Kannur
Executing Office Keezhallur PH Sn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Keezhallur PH Sn AE
Date: 27/06/2025

Work in progress | 78% Completed

3 Km of pipeline laid .Work stopped due to monsoon..

Keezhallur PH Sn AE
Date: 17/06/2025

Work in progress | 78% Completed